Modeling of wells overhaul period on the base of operating practices data

It is known that Azerbaijanian onshore oil and gas fields are developed on the late stages. These fields are characterized by depletion of production objects, pressure drop, gradual decreasing of production and overhaul period, increasing of water cutting of production and etc. For the purpose of efficiently development and recovery finish it is necessary the activities for optimization operating practices, increasing of wells overhaul period, limiting of water cutting and etc. In connection with this and using actual production data of Sabunchu-Balakhany-Romany oilfield, mathematical experiments for increasing overhaul period have been carried out. On the base of correlation-regression analysis regression equations have been obtained. These equations connected the overhaul values with all considered operational aspects. Estimated calculations on the base of obtained equations show the increasing of overhaul values in according with appropriate operation parameters. Thus research results realized on the base of production date of considered oilfield provide possibilities for taking a decision in purpose of optimal control of wells overhaul.

Authors

Publication Details

Journal
Azerbaijan Oil Industry
Published
2024-12-15
DOI
https://doi.org/10.37474/0365-8554/2024-12-13-17
Primary Topic
Reservoir Engineering and Simulation Methods
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Modeling of wells overhaul period on the base of operating practices data

I.Z. Ahmadov, T.A. Ahmadova
Azerbaijan Oil Industry
Reservoir Engineering and Simulation Methods
article

Modeling of wells overhaul period on the base of operating practices data

I.Z. Ahmadov, T.A. Ahmadova
article en

Abstract

It is known that Azerbaijanian onshore oil and gas fields are developed on the late stages. These fields are characterized by depletion of production objects, pressure drop, gradual decreasing of production and overhaul period, increasing of water cutting of production and etc. For the purpose of efficiently development and recovery finish it is necessary the activities for optimization operating practices, increasing of wells overhaul period, limiting of water cutting and etc. In connection with this and using actual production data of Sabunchu-Balakhany-Romany oilfield, mathematical experiments for increasing overhaul period have been carried out. On the base of correlation-regression analysis regression equations have been obtained. These equations connected the overhaul values with all considered operational aspects. Estimated calculations on the base of obtained equations show the increasing of overhaul values in according with appropriate operation parameters. Thus research results realized on the base of production date of considered oilfield provide possibilities for taking a decision in purpose of optimal control of wells overhaul.

Azerbaijan Oil Industry(12)
Openalex Percentile: Top 63%
Reservoir Engineering and Simulation Methods
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.