Duration-cost optimization in earthmoving operations using NSGA-II and simulation techniques

Innovative approaches for optimizing earthmoving fleets have been proposed in the field of construction management. Despite the emerging productivity analysis and optimization technologies, existing studies have witnessed the difficulty of real-life data collection on-site. Accordingly, this paper proposes a synthetic data generation method using the information extracted from the Korean Construction Standard Productivity Rate (CSPR) document. The extracted information was recalculated to activity times that were used as input in a Discrete Event Simulation (DES) model using the WebCyclone technique for producing synthetic data for conducting a productivity-prediction model-development practice using an Artificial Neural Network, XGBOOST, Random Forest and Duration-Cost optimization practice using non-dominated Sorting Genetic Algorithm II (NSGA-II). The comparison results showed that all three methods provide excellent goodness of fit and the NSGA-II can successfully deduce the Pareto front for Duration-Cost optimization.

Authors

Institutions

Publication Details

Journal
Journal of Asian Architecture and Building Engineering
Published
2025-03-13
DOI
https://doi.org/10.1080/13467581.2025.2472726
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Duration-cost optimization in earthmoving operations using NSGA-II and simulation techniques

Hyoung Jin Choi, Yongho Ko, Kheang Ngov, Seung Woo Han
Journal of Asian Architecture and Building Engineering
BIM and Construction Integration
article

Duration-cost optimization in earthmoving operations using NSGA-II and simulation techniques

Hyoung Jin Choi, Yongho Ko, Kheang Ngov, Seung Woo Han
article en

Abstract

Innovative approaches for optimizing earthmoving fleets have been proposed in the field of construction management. Despite the emerging productivity analysis and optimization technologies, existing studies have witnessed the difficulty of real-life data collection on-site. Accordingly, this paper proposes a synthetic data generation method using the information extracted from the Korean Construction Standard Productivity Rate (CSPR) document. The extracted information was recalculated to activity times that were used as input in a Discrete Event Simulation (DES) model using the WebCyclone technique for producing synthetic data for conducting a productivity-prediction model-development practice using an Artificial Neural Network, XGBOOST, Random Forest and Duration-Cost optimization practice using non-dominated Sorting Genetic Algorithm II (NSGA-II). The comparison results showed that all three methods provide excellent goodness of fit and the NSGA-II can successfully deduce the Pareto front for Duration-Cost optimization.

Journal of Asian Architecture and Building EngineeringVol. 25(2)
Inha University (KR)
National Research Foundation of Korea
Openalex Percentile: Top 96%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Duration-cost optimization in earthmoving operations using NSGA-II and simulation techniques — Hyoung Jin Choi, Yongho Ko, et al. · Journal of Asian Architecture and Building Engineering (2025) | TGRS Research Map | TGRS