Evaluasi Kinerja Waktu dan Biaya Proyek Melalui Pengaplikasian Metode Earned Value Studi Kasus Pada Pembangunan Ruas Jalan Sp. Armed Rumah-Great Kec. Biru-Biru Kab. Deli Serdang

Project delays are caused by lack of good control, which affects the time and cost of completion, in determining and knowing the time performance and cost performance of the SP. Armed-Rumah Great Road Construction Project, Biru-Biru District, Deli Serdang Regency. Using the Earned Value method. Based on the results, the results of the time performance from month 1 to month 3 of the project experienced delays, this is indicated by the Schedule Variant (SV) indicator which has a negative value of Rp. - 356,103,446.04 or Schedule Performance Index (SPI) = 0.828 <1. In the 4th month it was faster than the planned schedule, this is indicated by the Schedule Variant (SV) indicator which has a positive value of Rp. 96,183,088.74 or Schedule Performance Index (SPI) = 1.019>1. And in the 5th and 6th months the schedule performance index (SPI) value shows a value of 1 which means that the construction project work is in accordance. Meanwhile, for cost performance from month 1 to month 3, it incurred smaller costs than planned, this is indicated by the negative Cost Variance (CV) indicator of Rp. -150,413,906.18 or Cost Performance Index (CPI) = 0.920 <1. In month 4 to month 6, the Cost Variance CV value is above the X axis with a positive value of Rp. 829,560,555.98 or Cost Performance Index (CPI) = 1.110 >1 due to the addition of labor and additional working hours in project implementation.

Authors

Institutions

Publication Details

Journal
Majalah Ilmiah METHODA
Published
2024-12-31
DOI
https://doi.org/10.46880/methoda.vol14no3.pp403-412
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluasi Kinerja Waktu dan Biaya Proyek Melalui Pengaplikasian Metode Earned Value Studi Kasus Pada Pembangunan Ruas Jalan Sp. Armed Rumah-Great Kec. Biru-Biru Kab. Deli Serdang

Sederhana Laia, Sheila Hani, Rini Rini
Majalah Ilmiah METHODA
Management and Optimization Techniques
article

Evaluasi Kinerja Waktu dan Biaya Proyek Melalui Pengaplikasian Metode Earned Value Studi Kasus Pada Pembangunan Ruas Jalan Sp. Armed Rumah-Great Kec. Biru-Biru Kab. Deli Serdang

Sederhana Laia, Sheila Hani, Rini Rini
article en

Abstract

Project delays are caused by lack of good control, which affects the time and cost of completion, in determining and knowing the time performance and cost performance of the SP. Armed-Rumah Great Road Construction Project, Biru-Biru District, Deli Serdang Regency. Using the Earned Value method. Based on the results, the results of the time performance from month 1 to month 3 of the project experienced delays, this is indicated by the Schedule Variant (SV) indicator which has a negative value of Rp. - 356,103,446.04 or Schedule Performance Index (SPI) = 0.828 <1. In the 4th month it was faster than the planned schedule, this is indicated by the Schedule Variant (SV) indicator which has a positive value of Rp. 96,183,088.74 or Schedule Performance Index (SPI) = 1.019>1. And in the 5th and 6th months the schedule performance index (SPI) value shows a value of 1 which means that the construction project work is in accordance. Meanwhile, for cost performance from month 1 to month 3, it incurred smaller costs than planned, this is indicated by the negative Cost Variance (CV) indicator of Rp. -150,413,906.18 or Cost Performance Index (CPI) = 0.920 <1. In month 4 to month 6, the Cost Variance CV value is above the X axis with a positive value of Rp. 829,560,555.98 or Cost Performance Index (CPI) = 1.110 >1 due to the addition of labor and additional working hours in project implementation.

Majalah Ilmiah METHODAVol. 14(3)
Universitas Pembinaan Masyarakat Indonesia Medan (ID)
Openalex Percentile: Top 52%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Evaluasi Kinerja Waktu dan Biaya Proyek Melalui Pengaplikasian Metode Earned Value Studi Kasus Pada Pembangunan Ruas Jalan Sp. Armed Rumah-Great Kec. Biru-Biru Kab. Deli Serdang — Sederhana Laia, Sheila Hani, et al. · Majalah Ilmiah METHODA (2024) | TGRS Research Map | TGRS