Research on test performance and optimisation of 500 kV CVT under overvoltage

Capacitive voltage transformers (CVTs) are widely deployed in substations, used to monitor the field voltage signal, to ensure the safe operation of the power system. With the increasing voltage level of the power system, the system is affected by lightning, operating and other factors, which may cause excessive voltage in the power system, accelerate equipment aging, causing damage to power equipment. To improve the ability of the system to deal with overvoltage hazards, firstly this paper carries out operation overvoltage and lightning overvoltage tests on CVT, which added fix capacitance to improve transient responsiveness. Then, an equivalent circuit model of the shock voltage generator and CVT is built. Finally, by means of simulation, the cause of the distortion or error of the testing is analyzed, which lays the foundation for the subsequent improvement of the CVT device.

Authors

Institutions

Publication Details

Journal
IET conference proceedings.
Published
2025-03-01
DOI
https://doi.org/10.1049/icp.2025.0628
Primary Topic
Power Systems and Technologies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on test performance and optimisation of 500 kV CVT under overvoltage

Haoyang Tian, Shuo Guan, Lin He, Liming Wang et al.
IET conference proceedings.
Power Systems and Technologies
article

Research on test performance and optimisation of 500 kV CVT under overvoltage

Haoyang Tian, Shuo Guan, Lin He, Liming Wang, Yakun Liu, Dandan Zhao, Rong Xiao, Donghuang Luo
article en

Abstract

Capacitive voltage transformers (CVTs) are widely deployed in substations, used to monitor the field voltage signal, to ensure the safe operation of the power system. With the increasing voltage level of the power system, the system is affected by lightning, operating and other factors, which may cause excessive voltage in the power system, accelerate equipment aging, causing damage to power equipment. To improve the ability of the system to deal with overvoltage hazards, firstly this paper carries out operation overvoltage and lightning overvoltage tests on CVT, which added fix capacitance to improve transient responsiveness. Then, an equivalent circuit model of the shock voltage generator and CVT is built. Finally, by means of simulation, the cause of the distortion or error of the testing is analyzed, which lays the foundation for the subsequent improvement of the CVT device.

IET conference proceedings.Vol. 2024(33)
Shanghai Jiao Tong University (CN), Shanghai Electric (China) (CN)
Affordable and clean energy
Openalex Percentile: Top 96%
Power Systems and Technologies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Research on test performance and optimisation of 500 kV CVT under overvoltage — Haoyang Tian, Shuo Guan, et al. · IET conference proceedings. (2025) | TGRS Research Map | TGRS