Does Practice Make Perfect? A Longitudinal Analysis of the Contractual Governance of Ireland's First Public‐Private Partnership

ABSTRACT This paper examines how contractual governance in a public–private partnership evolved over a 16‐year period. It adopts a novel approach by revisiting an earlier analysis of Ireland's first PPP contract for school's infrastructure. We examine contractual governance at two distinct levels: the contract management level (between government and contractor) and the operational level (between school principals and facilities managers). We find that contractual governance between contracting parties has remained transactional but is now characterized by higher levels of trust and cooperation. However, we find that contractual governance has shifted from transactional to relational at the operational level. A number of factors have contributed to the evolution toward increased relational governance. These include the transfer of contract management to a newly established specialized PPP procurement agency, changes in personnel involved in the project, and the adoption of a more devolved approach to facilities management through the introduction of on‐site facilities managers.

Authors

Institutions

Publication Details

Journal
Public Administration
Published
2025-03-08
DOI
https://doi.org/10.1111/padm.13059
Citations
1
Primary Topic
Public-Private Partnership Projects
Type
article
Field-Weighted Citation Impact
2.23
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Does Practice Make Perfect? A Longitudinal Analysis of the Contractual Governance of Ireland's First Public‐Private Partnership

Cian O’Shea, Dónal Palcic, Eoin Reeves
1 citations
Public Administration
Public-Private Partnership Projects
2.23
article

Does Practice Make Perfect? A Longitudinal Analysis of the Contractual Governance of Ireland's First Public‐Private Partnership

Cian O’Shea, Dónal Palcic, Eoin Reeves
article en
1 citations

Abstract

ABSTRACT This paper examines how contractual governance in a public–private partnership evolved over a 16‐year period. It adopts a novel approach by revisiting an earlier analysis of Ireland's first PPP contract for school's infrastructure. We examine contractual governance at two distinct levels: the contract management level (between government and contractor) and the operational level (between school principals and facilities managers). We find that contractual governance between contracting parties has remained transactional but is now characterized by higher levels of trust and cooperation. However, we find that contractual governance has shifted from transactional to relational at the operational level. A number of factors have contributed to the evolution toward increased relational governance. These include the transfer of contract management to a newly established specialized PPP procurement agency, changes in personnel involved in the project, and the adoption of a more devolved approach to facilities management through the introduction of on‐site facilities managers.

Public AdministrationVol. 103(4)
Trinity College Dublin (IE), University of Limerick (IE)
Openalex Percentile: Top 13%
Public-Private Partnership Projects
2.23
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Does Practice Make Perfect? A Longitudinal Analysis of the Contractual Governance of Ireland's First Public‐Private Partnership — Cian O’Shea, Dónal Palcic, et al. · Public Administration (2025) | TGRS Research Map | TGRS