Optimization of Workstation Capacity using the Theory of Constraints Approach to Increase Production Output

A manufacturing company in Surabaya that produces various metal-based products is facing bottleneck issues, particularly in the production of steel doors and fire doors, due to an imbalance in machine capacity and cycle time. This problem has led to an accumulation of semi-finished goods and a decline in production efficiency. To address this issue, this study applies the Theory of Constraints (TOC) to redesign production planning through five key stages. Based on Rough-Cut Capacity Planning (RCCP) calculations, bottlenecks were identified at the bending workstation (SK-2), assembly workstation (SK-3), and painting workstation (SK-5). To mitigate these constraints, an additional 7 hours of overtime was implemented at these three workstations from July to November 2024. This strategy successfully increased fire door production from 89 units with a throughput of Rp178,000,000 to 167 units with a throughput of Rp334,000,000, reflecting a growth of Rp156,000,000 (46.7%). These findings demonstrate that the proposed approach is effective in optimizing throughput and maximizing production capacity utilization.

Authors

Institutions

Publication Details

Journal
SISTEMASI
Published
2025-03-04
DOI
https://doi.org/10.32520/stmsi.v14i2.5033
Primary Topic
Operations Management Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimization of Workstation Capacity using the Theory of Constraints Approach to Increase Production Output

Enny Aryanny, Fadilla Umeida Putri
SISTEMASI
Operations Management Techniques
article

Optimization of Workstation Capacity using the Theory of Constraints Approach to Increase Production Output

Enny Aryanny, Fadilla Umeida Putri
article en

Abstract

A manufacturing company in Surabaya that produces various metal-based products is facing bottleneck issues, particularly in the production of steel doors and fire doors, due to an imbalance in machine capacity and cycle time. This problem has led to an accumulation of semi-finished goods and a decline in production efficiency. To address this issue, this study applies the Theory of Constraints (TOC) to redesign production planning through five key stages. Based on Rough-Cut Capacity Planning (RCCP) calculations, bottlenecks were identified at the bending workstation (SK-2), assembly workstation (SK-3), and painting workstation (SK-5). To mitigate these constraints, an additional 7 hours of overtime was implemented at these three workstations from July to November 2024. This strategy successfully increased fire door production from 89 units with a throughput of Rp178,000,000 to 167 units with a throughput of Rp334,000,000, reflecting a growth of Rp156,000,000 (46.7%). These findings demonstrate that the proposed approach is effective in optimizing throughput and maximizing production capacity utilization.

SISTEMASIVol. 14(2)
University of Pembangunan Nasional Veteran Jawa Timur (ID)
Affordable and clean energy
Openalex Percentile: Top 95%
Operations Management Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Optimization of Workstation Capacity using the Theory of Constraints Approach to Increase Production Output — Enny Aryanny, Fadilla Umeida Putri · SISTEMASI (2025) | TGRS Research Map | TGRS