A Study on the Project Scheduling Problem with Uncertainty of Resources: Focusing on Rental Resources Requiring Reservation

The inherent uncertainty of a project causes a difference between the project plan and execution, and efforts are needed to reduce the project loss caused by this difference. Accordingly, in research on the project scheduling problem, research on the deterministic model that finds the optimal combination of fixed elements, such as the Resource Contained Project Scheduling Problem (RCPSP), which considers resource constraints, and the Stochastic RCPSP (SRCPSP), which applies uncertainty probabilistically, are being actively studied. This study deals with the case where there are resources required for project execution that must be procured through external reservation (rental), and there is uncertainty in the availability of the corresponding resources at the time of schedule rewriting due to a change in the preceding schedule. To this end, a mathematical model was developed that probabilistically added uncertainty about the availability of resources that must be procured through external reservations (rentals) at the time of schedule rewriting that occurs in the SRCPSP model with uncertainty in the period, and the distribution of the usage points of specific activities that use resources that must be procured through reservations (rentals) was obtained using simulation techniques. Afterwards, the distribution of the usage points of specific activities was appropriately applied to the initial schedule, and an algorithm for improving the average objective function value was developed. According to the simulation results, under the same conditions, the average objective function value of the simulation using the initial schedule after improvement was improved compared to before improvement, proving the validity of the model presented in this study. This study differs from previous studies in that it additionally considered uncertainty about the availability of external rental resources as a probabilistic factor based on the existing SRCPSP model. In addition, it is significant in that the uncertainty about changes in external resources was applied to the schedule problem at the time of project reevaluation.

Authors

Publication Details

Journal
The Academic Society of Global Business Administration
Published
2025-02-28
DOI
https://doi.org/10.38115/asgba.2025.22.1.114
Primary Topic
Software Engineering Techniques and Practices
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Study on the Project Scheduling Problem with Uncertainty of Resources: Focusing on Rental Resources Requiring Reservation

Doo Hee Lee, Jong Ho Kim, Tae Ho Ahn
The Academic Society of Global Business Administration
Software Engineering Techniques and Practices
article

A Study on the Project Scheduling Problem with Uncertainty of Resources: Focusing on Rental Resources Requiring Reservation

Doo Hee Lee, Jong Ho Kim, Tae Ho Ahn
article en

Abstract

The inherent uncertainty of a project causes a difference between the project plan and execution, and efforts are needed to reduce the project loss caused by this difference. Accordingly, in research on the project scheduling problem, research on the deterministic model that finds the optimal combination of fixed elements, such as the Resource Contained Project Scheduling Problem (RCPSP), which considers resource constraints, and the Stochastic RCPSP (SRCPSP), which applies uncertainty probabilistically, are being actively studied. This study deals with the case where there are resources required for project execution that must be procured through external reservation (rental), and there is uncertainty in the availability of the corresponding resources at the time of schedule rewriting due to a change in the preceding schedule. To this end, a mathematical model was developed that probabilistically added uncertainty about the availability of resources that must be procured through external reservations (rentals) at the time of schedule rewriting that occurs in the SRCPSP model with uncertainty in the period, and the distribution of the usage points of specific activities that use resources that must be procured through reservations (rentals) was obtained using simulation techniques. Afterwards, the distribution of the usage points of specific activities was appropriately applied to the initial schedule, and an algorithm for improving the average objective function value was developed. According to the simulation results, under the same conditions, the average objective function value of the simulation using the initial schedule after improvement was improved compared to before improvement, proving the validity of the model presented in this study. This study differs from previous studies in that it additionally considered uncertainty about the availability of external rental resources as a probabilistic factor based on the existing SRCPSP model. In addition, it is significant in that the uncertainty about changes in external resources was applied to the schedule problem at the time of project reevaluation.

The Academic Society of Global Business AdministrationVol. 22(1)
Openalex Percentile: Top 95%
Software Engineering Techniques and Practices
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A Study on the Project Scheduling Problem with Uncertainty of Resources: Focusing on Rental Resources Requiring Reservation — Doo Hee Lee, Jong Ho Kim, et al. · The Academic Society of Global Business Administration (2025) | TGRS Research Map | TGRS