Sustainable building production adopting an optimized BIM phasing system

Sustainable building production could be achieved through better economic efficiency, reduced site waste, and a safe working environment. The identification of the creation phase for each element in the building information model (BIM) is manually done by experienced engineers able to integrate technical construction constraints and an appropriate workflow of construction activities. It is a difficult and complex task to be done. Experienced engineers iterate this operation several times until an adequate solution is achieved without real possibility of optimization. The development of an assistance tool to optimize phase identification of BIM elements included in the repetitive floor plan considering varied evaluation criteria and technical construction constraints should lead to significant economic and environmental profits: reduction of needed construction resources and related waste, improvement of construction quality, and better conditions of site safety. The optimization tool presented in this paper provides better solutions for repetitive floor plans specifically through balanced quantities of work hours and a lower quantity of needed formworks. A reduction of around 10% of labour and 25% of non-used formwork is achieved, which significantly improves site safety, productivity, and profitability. The validity of the presented results is substantiated by multiple examples from real construction sites that have been analyzed in this study.

Authors

Publication Details

Journal
The Journal of Engineering Research [TJER]
Published
2025-03-04
DOI
https://doi.org/10.53540/tjer.vol21iss1pp17-22
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Sustainable building production adopting an optimized BIM phasing system

Ali Istanbullu, Elsayed Ali Omar
The Journal of Engineering Research [TJER]
BIM and Construction Integration
article

Sustainable building production adopting an optimized BIM phasing system

Ali Istanbullu, Elsayed Ali Omar
article en

Abstract

Sustainable building production could be achieved through better economic efficiency, reduced site waste, and a safe working environment. The identification of the creation phase for each element in the building information model (BIM) is manually done by experienced engineers able to integrate technical construction constraints and an appropriate workflow of construction activities. It is a difficult and complex task to be done. Experienced engineers iterate this operation several times until an adequate solution is achieved without real possibility of optimization. The development of an assistance tool to optimize phase identification of BIM elements included in the repetitive floor plan considering varied evaluation criteria and technical construction constraints should lead to significant economic and environmental profits: reduction of needed construction resources and related waste, improvement of construction quality, and better conditions of site safety. The optimization tool presented in this paper provides better solutions for repetitive floor plans specifically through balanced quantities of work hours and a lower quantity of needed formworks. A reduction of around 10% of labour and 25% of non-used formwork is achieved, which significantly improves site safety, productivity, and profitability. The validity of the presented results is substantiated by multiple examples from real construction sites that have been analyzed in this study.

The Journal of Engineering Research [TJER]Vol. 21(1)
Openalex Percentile: Top 96%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Sustainable building production adopting an optimized BIM phasing system — Ali Istanbullu, Elsayed Ali Omar · The Journal of Engineering Research [TJER] (2025) | TGRS Research Map | TGRS