Performance Index Analysis on the Construction of Probolinggo - Banyuwangi Toll Road Package 3

This study analyzes the performance index of the Probolinggo-Banyuwangi Toll Road Package 3 construction project using the Earned Value Method (EVM) to evaluate time and cost performance. Infrastructure projects, particularly toll roads, play a vital role in enhancing regional connectivity and economic growth. However, large-scale construction projects frequently face challenges such as cost overruns and delays. The Earned Value Method provides a comprehensive framework for measuring project performance by comparing planned costs, actual expenditures, and completed work. This research employs key performance indicators, including Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), and Actual Cost of Work Performed (ACWP), to determine the Schedule Performance Index (SPI) and Cost Performance Index (CPI). The findings reveal that the project experienced schedule delays, with an SPI of 0.93, indicating that work progress was behind the planned schedule. However, the project maintained cost efficiency, as shown by a CPI of 1.06, reflecting lower actual costs than budgeted. The study highlights the importance of continuous performance monitoring using EVM to identify potential risks, optimize resource allocation, and support timely decision-making. The results provide valuable insights for project managers to improve efficiency and ensure project success in large-scale infrastructure developments.

Authors

Institutions

Publication Details

Journal
Enrichment Journal of Multidisciplinary Research and Development
Published
2025-02-27
DOI
https://doi.org/10.55324/enrichment.v2i11.311
Primary Topic
Geotechnical and construction materials studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Performance Index Analysis on the Construction of Probolinggo - Banyuwangi Toll Road Package 3

Hanie Teki Tjendani, Esti Wulandari, Ummatus Sholikhah
Enrichment Journal of Multidisciplinary Research and Development
Geotechnical and construction materials studies
article

Performance Index Analysis on the Construction of Probolinggo - Banyuwangi Toll Road Package 3

Hanie Teki Tjendani, Esti Wulandari, Ummatus Sholikhah
article en

Abstract

This study analyzes the performance index of the Probolinggo-Banyuwangi Toll Road Package 3 construction project using the Earned Value Method (EVM) to evaluate time and cost performance. Infrastructure projects, particularly toll roads, play a vital role in enhancing regional connectivity and economic growth. However, large-scale construction projects frequently face challenges such as cost overruns and delays. The Earned Value Method provides a comprehensive framework for measuring project performance by comparing planned costs, actual expenditures, and completed work. This research employs key performance indicators, including Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), and Actual Cost of Work Performed (ACWP), to determine the Schedule Performance Index (SPI) and Cost Performance Index (CPI). The findings reveal that the project experienced schedule delays, with an SPI of 0.93, indicating that work progress was behind the planned schedule. However, the project maintained cost efficiency, as shown by a CPI of 1.06, reflecting lower actual costs than budgeted. The study highlights the importance of continuous performance monitoring using EVM to identify potential risks, optimize resource allocation, and support timely decision-making. The results provide valuable insights for project managers to improve efficiency and ensure project success in large-scale infrastructure developments.

Enrichment Journal of Multidisciplinary Research and DevelopmentVol. 2(11)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 96%
Geotechnical and construction materials studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.