Penjadwalan Tambang (Mine Schedulling) untuk Memenuhi Target Produksi Tahunan Batubara PT XYZ di Kecamatan Loa Janan, Kabupaten Kutai Kertanegara, Provinsi Kalimantan Timur

Abstract. PT XYZ is a company which operates in the coal mining sector located in Loa Janan District, Kutai Kertanegara Regency, East Kalimantan Province. For the mining activities used by the company, an open-pit mining system with the contour mining method is employed. The company has a coal resource amounting to 27,904,066.32 tons. The mine scheduling production plan has not yet been carried out. Therefore, this research aims to design the mining layout, plan the mine scheduling, and determine the amount of reserves mined per year. In this research, the design of mining and scheduling of mine production will be carried out. The design and scheduling need to be carried out as stages of mine planning. The results of the mine planning and scheduling then become production targets that will later be used as a reference in the implementation of mining. Based on the results of the design and scheduling (mine scheduling), a 10-year mine life plan was obtained based on coal reserves amounting to 10,314,327 tons. For the first year, an area of 15.30 Ha is planned with a coal production target of 1,886,510.15 tons. The second year has an area of 10.32 Ha with a coal production target of 1,031,432.70 tons. The third year has an area of 11.74 Ha with a coal production target of 1,021,452.70 tons. The fourth year has an area of 12.50 Ha with a coal production target of 1,031,432.70 tons. The fifth year has an area of 11.39 Ha with a coal production target of 1,217,767.95 tons. The sixth year has an area of 9.24 Ha with a coal production target of 1,031,432.70 tons. The seventh year has an area of 8.32 Ha with a coal production target of 1,031,532.60 tons. The eighth year has an area of 7.53 Ha with a coal production target of 1,031,432.70 tons. The ninth year has an area of 7.86 Ha with a coal production target of 1,031,432.70 tons. And for the last year, an area of 5.12 Ha is planned with a coal production target of 318,742.19 tons. Abstrak. PT XYZ merupakan suatu perusahaan yang bergerak di bidang pertambangan batubara yang berlokasi di Kecamatan Loa Janan, kabupaten Kutai Kertanegara, Provinsi Kalimantan Timur. Untuk kegiatan penambangan yang digunakan pada perusahaan tersebut memakai sistem tambang terbuka dengan metode contour mining. Perusahaan memiliki jumlah sumberdaya batubara sebesar 27,904,066.32 ton. Kegiatan rencana penjadwalan produksi tambang (mine schedulling) belum dilakukan. Sehingga penelitian ini memiliki tujuan yaitu merancangan desain penambangan, merencanakan penjadwalan tambang dan mengetahui berapa jumlah cadangan yang tertambang per tahun. Dalam penelitian ini nantinya akan melakukan perancangan desain penambangan dan penjadwalan produksi tambang. Perancangan dan juga penjadwalan perlu untuk dilakukan sebagai tahapan dari perencanaan tambang. Hasil dari perancangan serta penjadwalan tambang tersebut kemudian menjadi target produksi yang nantinya akan digunakan sebagai acuan dalam pelaksanaan penambangan. Berdasarkan hasil perancangan desain dan penjadwalan (mine scheduling) yang mana didapatkan rencana umur tambang selama 10 tahun berdasarkan jumlah cadangan batubara sebesar 10.314,327 ton. Untuk tahun pertama mempunyai area seluas 15,30 Ha dengan rencana produksi batubara didapatkan sebesar 1.886.510,15 Ton, tahun kedua mempunyai area seluas 10,32 Ha dengan rencana produksi batubara sebesar 1.031.432,70 Ton, tahun ketiga mempunyai area seluas 11,74 Ha dengan rencana produksi batubara sebesar 1.021.452,70 Ton, tahun keempat mempunyai area seluas 12,50 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, tahun kelima mempunyai area seluas 11,39 Ha dengan rencana produksi batubara sebesar 1,217,767.95 Ton, tahun keenam mempunyai area seluas 9,24 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, tahun ketujuh mempunyai area seluas 8,32 Ha dengan rencana produksi batubara sebesar 1,031,532.60 Ton, tahun kedelapan mempunyai area seluas 7,53 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, tahun kesembilan mempunyai area seluas 7,86 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, dan untuk tahun terakhir mempunyai area seluas 5,12 Ha didapatkan rencana produksi batubara sebesar 318,742.19 Ton

Authors

Institutions

Publication Details

Journal
Bandung Conference Series Mining Engineering
Published
2025-02-03
DOI
https://doi.org/10.29313/bcsme.v5i1.17317
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Penjadwalan Tambang (Mine Schedulling) untuk Memenuhi Target Produksi Tahunan Batubara PT XYZ di Kecamatan Loa Janan, Kabupaten Kutai Kertanegara, Provinsi Kalimantan Timur

Zaenal, Iswandaru, R Putra
Bandung Conference Series Mining Engineering
Mining Techniques and Economics
article

Penjadwalan Tambang (Mine Schedulling) untuk Memenuhi Target Produksi Tahunan Batubara PT XYZ di Kecamatan Loa Janan, Kabupaten Kutai Kertanegara, Provinsi Kalimantan Timur

Zaenal, Iswandaru, R Putra
article en

Abstract

Abstract. PT XYZ is a company which operates in the coal mining sector located in Loa Janan District, Kutai Kertanegara Regency, East Kalimantan Province. For the mining activities used by the company, an open-pit mining system with the contour mining method is employed. The company has a coal resource amounting to 27,904,066.32 tons. The mine scheduling production plan has not yet been carried out. Therefore, this research aims to design the mining layout, plan the mine scheduling, and determine the amount of reserves mined per year. In this research, the design of mining and scheduling of mine production will be carried out. The design and scheduling need to be carried out as stages of mine planning. The results of the mine planning and scheduling then become production targets that will later be used as a reference in the implementation of mining. Based on the results of the design and scheduling (mine scheduling), a 10-year mine life plan was obtained based on coal reserves amounting to 10,314,327 tons. For the first year, an area of 15.30 Ha is planned with a coal production target of 1,886,510.15 tons. The second year has an area of 10.32 Ha with a coal production target of 1,031,432.70 tons. The third year has an area of 11.74 Ha with a coal production target of 1,021,452.70 tons. The fourth year has an area of 12.50 Ha with a coal production target of 1,031,432.70 tons. The fifth year has an area of 11.39 Ha with a coal production target of 1,217,767.95 tons. The sixth year has an area of 9.24 Ha with a coal production target of 1,031,432.70 tons. The seventh year has an area of 8.32 Ha with a coal production target of 1,031,532.60 tons. The eighth year has an area of 7.53 Ha with a coal production target of 1,031,432.70 tons. The ninth year has an area of 7.86 Ha with a coal production target of 1,031,432.70 tons. And for the last year, an area of 5.12 Ha is planned with a coal production target of 318,742.19 tons. Abstrak. PT XYZ merupakan suatu perusahaan yang bergerak di bidang pertambangan batubara yang berlokasi di Kecamatan Loa Janan, kabupaten Kutai Kertanegara, Provinsi Kalimantan Timur. Untuk kegiatan penambangan yang digunakan pada perusahaan tersebut memakai sistem tambang terbuka dengan metode contour mining. Perusahaan memiliki jumlah sumberdaya batubara sebesar 27,904,066.32 ton. Kegiatan rencana penjadwalan produksi tambang (mine schedulling) belum dilakukan. Sehingga penelitian ini memiliki tujuan yaitu merancangan desain penambangan, merencanakan penjadwalan tambang dan mengetahui berapa jumlah cadangan yang tertambang per tahun. Dalam penelitian ini nantinya akan melakukan perancangan desain penambangan dan penjadwalan produksi tambang. Perancangan dan juga penjadwalan perlu untuk dilakukan sebagai tahapan dari perencanaan tambang. Hasil dari perancangan serta penjadwalan tambang tersebut kemudian menjadi target produksi yang nantinya akan digunakan sebagai acuan dalam pelaksanaan penambangan. Berdasarkan hasil perancangan desain dan penjadwalan (mine scheduling) yang mana didapatkan rencana umur tambang selama 10 tahun berdasarkan jumlah cadangan batubara sebesar 10.314,327 ton. Untuk tahun pertama mempunyai area seluas 15,30 Ha dengan rencana produksi batubara didapatkan sebesar 1.886.510,15 Ton, tahun kedua mempunyai area seluas 10,32 Ha dengan rencana produksi batubara sebesar 1.031.432,70 Ton, tahun ketiga mempunyai area seluas 11,74 Ha dengan rencana produksi batubara sebesar 1.021.452,70 Ton, tahun keempat mempunyai area seluas 12,50 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, tahun kelima mempunyai area seluas 11,39 Ha dengan rencana produksi batubara sebesar 1,217,767.95 Ton, tahun keenam mempunyai area seluas 9,24 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, tahun ketujuh mempunyai area seluas 8,32 Ha dengan rencana produksi batubara sebesar 1,031,532.60 Ton, tahun kedelapan mempunyai area seluas 7,53 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, tahun kesembilan mempunyai area seluas 7,86 Ha dengan rencana produksi batubara sebesar 1,031,432.70 Ton, dan untuk tahun terakhir mempunyai area seluas 5,12 Ha didapatkan rencana produksi batubara sebesar 318,742.19 Ton

Bandung Conference Series Mining EngineeringVol. 5(1)
Bandung Islamic University (ID)
Openalex Percentile: Top 96%
Mining Techniques and Economics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.