Improving a risk estimating method for the "Smart house" information system IT project

The object of this study is the IT project risk management process. The study solves the task to improve the accuracy of risk assessment in IT projects and, in particular, IT projects to design the information system (IS) "Smart House". Research into this area is mainly focused on the application of machine learning (ML) methods to improve the results of conventional evaluation methods. Issues related to quantitative risk assessment of IT projects to design the "Smart House" IS remain practically unexplored. During the study, it was proposed to use ML methods for preprocessing the raw data. For this purpose, a combined risk assessment method was devised. In this technique, methods of Support Vector Machine and Bayesian networks were applied to process the raw data. The results of their application were used as input data for Monte Carlo simulations. During the software implementation of the devised method, its technological stack was determined. Fragments of the program code are given, which describe the implementation of the basic elements of the combined method. The devised method and its software implementation were used to assess the risk of delay in the implementation of the IT project to design the "Smart House" IS. The evaluation results determine the expected duration of this IT project at 234.5 days, with a deviation range of 226–244 days (with a 95 % confidence interval). The results of a comparative analysis of the obtained estimates with estimates of the same risk obtained using the conventional Monte Carlo method show that the devised method provides higher reliability of forecasts. The application of research findings makes it possible to improve the quality of managing IT projects by increasing the accuracy and reliability of their risk assessments

Authors

Institutions

Publication Details

Journal
Eastern-European Journal of Enterprise Technologies
Published
2025-02-21
DOI
https://doi.org/10.15587/1729-4061.2025.322051
Primary Topic
Big Data and Business Intelligence
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Improving a risk estimating method for the "Smart house" information system IT project

Iryna Panforova, Nataliya Vasiltcova, Maksym Ievlanov, Yevhen Kliuvanskyi
Eastern-European Journal of Enterprise Technologies
Big Data and Business Intelligence
article

Improving a risk estimating method for the "Smart house" information system IT project

Iryna Panforova, Nataliya Vasiltcova, Maksym Ievlanov, Yevhen Kliuvanskyi
article en

Abstract

The object of this study is the IT project risk management process. The study solves the task to improve the accuracy of risk assessment in IT projects and, in particular, IT projects to design the information system (IS) "Smart House". Research into this area is mainly focused on the application of machine learning (ML) methods to improve the results of conventional evaluation methods. Issues related to quantitative risk assessment of IT projects to design the "Smart House" IS remain practically unexplored. During the study, it was proposed to use ML methods for preprocessing the raw data. For this purpose, a combined risk assessment method was devised. In this technique, methods of Support Vector Machine and Bayesian networks were applied to process the raw data. The results of their application were used as input data for Monte Carlo simulations. During the software implementation of the devised method, its technological stack was determined. Fragments of the program code are given, which describe the implementation of the basic elements of the combined method. The devised method and its software implementation were used to assess the risk of delay in the implementation of the IT project to design the "Smart House" IS. The evaluation results determine the expected duration of this IT project at 234.5 days, with a deviation range of 226–244 days (with a 95 % confidence interval). The results of a comparative analysis of the obtained estimates with estimates of the same risk obtained using the conventional Monte Carlo method show that the devised method provides higher reliability of forecasts. The application of research findings makes it possible to improve the quality of managing IT projects by increasing the accuracy and reliability of their risk assessments

Eastern-European Journal of Enterprise TechnologiesVol. 1(3 (133))
Kharkiv National University of Radio Electronics (UA)
Openalex Percentile: Top 94%
Big Data and Business Intelligence
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.