Development of a Hybrid Model for Risk Assessment and Management in Complex Road Infrastructure Projects

During the execution of road infrastructure projects, project managers face significant challenges, including financial, technical, regulatory, and operational risks. More than 90% of infrastructure projects have incurred costs exceeding initial estimates, impacting both completion timelines and the operational efficiency of road infrastructure. Effectively assessing and managing these risks is crucial for improving project outcomes and ensuring the sustainability of infrastructure investments. To address these challenges, this study developed a hybrid model for risk assessment and management in road infrastructure projects. The model quantifies risks across seven key categories: Design, External, Resource, Employer, Contractor, Engineer, and Project, based on three primary input factors: Environment coefficient, Contractual coefficient, and Design coefficient. Initially, various machine learning models, including linear regression, Random Forest, Gradient Boosting, Stacking Models, and neural networks, were applied to assess risk predictions. However, due to the specific nature of the dataset, these models did not achieve satisfactory predictive accuracy. As a result, fuzzy logic systems (Mamdani and Sugeno) were employed, demonstrating superior performance in modeling risk occurrence probabilities. Comparative analysis between these two fuzzy logic approaches revealed that the Sugeno model provided the most accurate predictions. The findings highlight the benefits of applying fuzzy logic for risk assessment in complex infrastructure projects, providing a structured framework for enhancing decision-making processes. This study provides a structured methodology for accurately predicting risks and enhancing project safety, efficiency, and long-term sustainability.

Authors

Institutions

Publication Details

Journal
Applied Sciences
Published
2025-03-04
DOI
https://doi.org/10.3390/app15052736
Citations
6
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
12.64
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Development of a Hybrid Model for Risk Assessment and Management in Complex Road Infrastructure Projects

Momčilo Đobrodolac, Zoran Stojadinović, Nevena Simić, Aleksandar Senić
6 citations
Applied Sciences
Construction Project Management and Performance
12.64
article

Development of a Hybrid Model for Risk Assessment and Management in Complex Road Infrastructure Projects

Momčilo Đobrodolac, Zoran Stojadinović, Nevena Simić, Aleksandar Senić
article en
6 citations

Abstract

During the execution of road infrastructure projects, project managers face significant challenges, including financial, technical, regulatory, and operational risks. More than 90% of infrastructure projects have incurred costs exceeding initial estimates, impacting both completion timelines and the operational efficiency of road infrastructure. Effectively assessing and managing these risks is crucial for improving project outcomes and ensuring the sustainability of infrastructure investments. To address these challenges, this study developed a hybrid model for risk assessment and management in road infrastructure projects. The model quantifies risks across seven key categories: Design, External, Resource, Employer, Contractor, Engineer, and Project, based on three primary input factors: Environment coefficient, Contractual coefficient, and Design coefficient. Initially, various machine learning models, including linear regression, Random Forest, Gradient Boosting, Stacking Models, and neural networks, were applied to assess risk predictions. However, due to the specific nature of the dataset, these models did not achieve satisfactory predictive accuracy. As a result, fuzzy logic systems (Mamdani and Sugeno) were employed, demonstrating superior performance in modeling risk occurrence probabilities. Comparative analysis between these two fuzzy logic approaches revealed that the Sugeno model provided the most accurate predictions. The findings highlight the benefits of applying fuzzy logic for risk assessment in complex infrastructure projects, providing a structured framework for enhancing decision-making processes. This study provides a structured methodology for accurately predicting risks and enhancing project safety, efficiency, and long-term sustainability.

Applied SciencesVol. 15(5)
University of Belgrade (RS), Saveetha University (IN)
Openalex Percentile: Top 2%
Construction Project Management and Performance
12.64
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.