Project delivery success and sustainability: comparative strategies in the post-pandemic era

Purpose This study aims to identify strategies and offer empirical recommendations for project managers and policymakers to enhance PDS in public construction projects in the post-pandemic era, focusing on KPIs using the 3D integration model. Design/methodology/approach This study uses a mixed-method approach to retrospectively evaluate the project management performance of 16 Australian public construction projects. Employing a project delivery success (PDS) model (the 3D integration model), it assesses delivery success across six key performance indicators (KPIs) to identify strategies for improving project outcomes in the post-pandemic era. Data collection involved interviews and document analysis, focusing on projects completed at different times and with various sizes. Findings The analysis highlights three critical KPIs – Value (scope/cost), Speed (scope/time) and Impact (scope/risk) – as significant determinants of project success. The study provides evidence that successful projects maximize Value and Speed and minimize Impact. Key strategies include improving remote work arrangements, investing in digital tools, adopting advanced procurement mechanisms and enhancing risk management processes. Practical implications For practitioners, the study offers actionable strategies to enhance the performance of public construction projects, focusing on maximizing Value, Speed and minimizing Impact. It suggests adopting advanced project management techniques, digital tools for collaboration and reevaluating procurement and risk management processes to navigate the post-pandemic challenges effectively. Originality/value This research contributes to the field by applying the 3D integration model to analyzing public construction projects during the COVID-19 pandemic, a novel approach in this context. It provides a unique empirical basis for recommendations bridging the gap between theoretical project management models and practical application in a post-pandemic world, thus offering significant value to academic research and practical project management in the public sector.

Authors

Publication Details

Journal
Management Decision
Published
2025-02-27
DOI
https://doi.org/10.1108/md-03-2024-0445
Citations
4
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
8.43
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Project delivery success and sustainability: comparative strategies in the post-pandemic era

Martin Skitmore, Carol K.H. Hon, Roksana Jahan Tumpa, Amir Naser Ghanbaripour
4 citations
Management Decision
Construction Project Management and Performance
8.43
article

Project delivery success and sustainability: comparative strategies in the post-pandemic era

Martin Skitmore, Carol K.H. Hon, Roksana Jahan Tumpa, Amir Naser Ghanbaripour
article en
4 citations

Abstract

Purpose This study aims to identify strategies and offer empirical recommendations for project managers and policymakers to enhance PDS in public construction projects in the post-pandemic era, focusing on KPIs using the 3D integration model. Design/methodology/approach This study uses a mixed-method approach to retrospectively evaluate the project management performance of 16 Australian public construction projects. Employing a project delivery success (PDS) model (the 3D integration model), it assesses delivery success across six key performance indicators (KPIs) to identify strategies for improving project outcomes in the post-pandemic era. Data collection involved interviews and document analysis, focusing on projects completed at different times and with various sizes. Findings The analysis highlights three critical KPIs – Value (scope/cost), Speed (scope/time) and Impact (scope/risk) – as significant determinants of project success. The study provides evidence that successful projects maximize Value and Speed and minimize Impact. Key strategies include improving remote work arrangements, investing in digital tools, adopting advanced procurement mechanisms and enhancing risk management processes. Practical implications For practitioners, the study offers actionable strategies to enhance the performance of public construction projects, focusing on maximizing Value, Speed and minimizing Impact. It suggests adopting advanced project management techniques, digital tools for collaboration and reevaluating procurement and risk management processes to navigate the post-pandemic challenges effectively. Originality/value This research contributes to the field by applying the 3D integration model to analyzing public construction projects during the COVID-19 pandemic, a novel approach in this context. It provides a unique empirical basis for recommendations bridging the gap between theoretical project management models and practical application in a post-pandemic world, thus offering significant value to academic research and practical project management in the public sector.

Management Decision
Openalex Percentile: Top 3%
Construction Project Management and Performance
8.43
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.