Total transfer capacity of the north Greece border: where are we now?

Nowadays, Regional Coordination Centers (RCCs) promote the coupling of the European electricity markets by performing on a daily basis the Coordinated Capacity Calculation (CCC), that aims to compute the maximum Total Transfer Capacity (TTC) on a secure and reliable way. In this paper, the impact of several factors on the TTC of the North Greece (NGR) border is quantified and presented. More specifically, during 2023 two crucial changes have been applied on the power system of the NGR border. The first change is the energization of the Maritza East - Nea Santa tie-line, which is a second tie-line between Greece and Bulgaria. The second change is the modification of the protection relay settings of the tie-lines between North Macedonia and Greece. These tie-lines are the Bitola - Meliti and Dubrovo - Thessaloniki. The analysis reveals that both changes had a positive impact, increasing considerably the transmission capability of the NGR border.

Authors

Institutions

Publication Details

Journal
IET conference proceedings.
Published
2025-02-01
DOI
https://doi.org/10.1049/icp.2024.4727
Primary Topic
Marine and environmental studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Total transfer capacity of the north Greece border: where are we now?

Eleftherios O. Kontis, Grigoris A. Dourbois, Alexandros Gisis, Petros Peitsinis et al.
IET conference proceedings.
Marine and environmental studies
article

Total transfer capacity of the north Greece border: where are we now?

Eleftherios O. Kontis, Grigoris A. Dourbois, Alexandros Gisis, Petros Peitsinis, Chrysi Panopoulou, Andronikos Koumis, Yannis Kampouris
article en

Abstract

Nowadays, Regional Coordination Centers (RCCs) promote the coupling of the European electricity markets by performing on a daily basis the Coordinated Capacity Calculation (CCC), that aims to compute the maximum Total Transfer Capacity (TTC) on a secure and reliable way. In this paper, the impact of several factors on the TTC of the North Greece (NGR) border is quantified and presented. More specifically, during 2023 two crucial changes have been applied on the power system of the NGR border. The first change is the energization of the Maritza East - Nea Santa tie-line, which is a second tie-line between Greece and Bulgaria. The second change is the modification of the protection relay settings of the tie-lines between North Macedonia and Greece. These tie-lines are the Bitola - Meliti and Dubrovo - Thessaloniki. The analysis reveals that both changes had a positive impact, increasing considerably the transmission capability of the NGR border.

IET conference proceedings.Vol. 2024(29)
University of Thessaly (GR), South Eastern Europe Telecommunications Academy (GR)
Openalex Percentile: Top 97%
Marine and environmental studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.