Analysis of The Delay in The Implementation of Toll Road Project Work

Infrastructure development is crucial for economic progress, and Indonesia has witnessed significant advancements in this sector, especially in toll road projects over the past decade. The Indonesian government, through the Ministry of Public Works and Housing (PUPR), is dedicated to infrastructure development to achieve the "Golden Indonesia" 2045 vision. Despite this commitment, many projects face delays, adversely affecting costs, quality, and timelines. This study investigates the causes of delays in toll road projects with case studies on two projects in Sumatra, one in Java, and one in Kalimantan. The research methods include literature review, data collection, and surveys distributed to project owners, supervision consultants, and contractors, followed by analysis of the survey results. Among 24 respondents, the predominant delay factors identified are unresolved land issues, improper scheduling, resource shortages, and unforeseen circumstances. Further analysis revealed that among the 16 delay causes related to land, five stem from non-technical aspects and 13 from technical aspects, with overlapping causes such as incomplete contract work types and unforeseen situations. The average risk value indicates that land-related delay factors have a higher impact compared to others. Specifically, the technical aspect risk value is 10.75, and the non-technical aspect is 12.33 on a maximum risk value scale of 25. These results highlight the critical need for effective land risk management to enhance efficiency and effectiveness in toll road project execution. This research aims to assist future project management, enrich civil engineering knowledge, and support the continuous growth of infrastructure development in Indonesia.

Authors

Institutions

Publication Details

Journal
Eduvest - Journal Of Universal Studies
Published
2025-02-20
DOI
https://doi.org/10.59188/eduvest.v5i2.1716
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of The Delay in The Implementation of Toll Road Project Work

Jati Irawan
Eduvest - Journal Of Universal Studies
Occupational Health and Safety Management
article

Analysis of The Delay in The Implementation of Toll Road Project Work

Jati Irawan
article en

Abstract

Infrastructure development is crucial for economic progress, and Indonesia has witnessed significant advancements in this sector, especially in toll road projects over the past decade. The Indonesian government, through the Ministry of Public Works and Housing (PUPR), is dedicated to infrastructure development to achieve the "Golden Indonesia" 2045 vision. Despite this commitment, many projects face delays, adversely affecting costs, quality, and timelines. This study investigates the causes of delays in toll road projects with case studies on two projects in Sumatra, one in Java, and one in Kalimantan. The research methods include literature review, data collection, and surveys distributed to project owners, supervision consultants, and contractors, followed by analysis of the survey results. Among 24 respondents, the predominant delay factors identified are unresolved land issues, improper scheduling, resource shortages, and unforeseen circumstances. Further analysis revealed that among the 16 delay causes related to land, five stem from non-technical aspects and 13 from technical aspects, with overlapping causes such as incomplete contract work types and unforeseen situations. The average risk value indicates that land-related delay factors have a higher impact compared to others. Specifically, the technical aspect risk value is 10.75, and the non-technical aspect is 12.33 on a maximum risk value scale of 25. These results highlight the critical need for effective land risk management to enhance efficiency and effectiveness in toll road project execution. This research aims to assist future project management, enrich civil engineering knowledge, and support the continuous growth of infrastructure development in Indonesia.

Eduvest - Journal Of Universal StudiesVol. 5(2)
Bandung Institute of Technology (ID)
Industry, innovation and infrastructure
Openalex Percentile: Top 95%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.