World’s First UHV Hybrid LCC–VSC MTDC Project: Experimental Tests and Onsite Commissioning

The WDD project is the world’s first multi-terminal UHVDC project that combines LCC-HVDC and VSC-HVDC. Such station-to-station hybrid UHVDC systems can make full use of the technical advantages of VSC to ride through the faults of AC system and improve the voltage support capability of power grids at the receiving end. One of the key challenges for the success of this project is to ensure that both the designs of the main equipment and the control functions meet the expected performance indices and technical specifications. For this, before being taken into operation, experimental tests based on a physical prototype followed by onsite commissioning are essential to verify the safety and reliability of equipment and system in various operating conditions. This article aims to introduce the experimental platform, key physical prototype tests based on the platform, and the key tests undertaken during system onsite commissioning.

Authors

Institutions

Publication Details

Journal
IEEE Power and Energy Magazine
Published
2025-02-26
DOI
https://doi.org/10.1109/mpe.2024.3451432
Primary Topic
HVDC Systems and Fault Protection
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

World’s First UHV Hybrid LCC–VSC MTDC Project: Experimental Tests and Onsite Commissioning

Yan Xiong, Changyue Zou, Yuebin Zhou, Shukai Xu et al.
IEEE Power and Energy Magazine
HVDC Systems and Fault Protection
article

World’s First UHV Hybrid LCC–VSC MTDC Project: Experimental Tests and Onsite Commissioning

Yan Xiong, Changyue Zou, Yuebin Zhou, Shukai Xu, Wei Wei, Tao Liu, Hong Rao, Yu Yang, Wanyu Cao
article en

Abstract

The WDD project is the world’s first multi-terminal UHVDC project that combines LCC-HVDC and VSC-HVDC. Such station-to-station hybrid UHVDC systems can make full use of the technical advantages of VSC to ride through the faults of AC system and improve the voltage support capability of power grids at the receiving end. One of the key challenges for the success of this project is to ensure that both the designs of the main equipment and the control functions meet the expected performance indices and technical specifications. For this, before being taken into operation, experimental tests based on a physical prototype followed by onsite commissioning are essential to verify the safety and reliability of equipment and system in various operating conditions. This article aims to introduce the experimental platform, key physical prototype tests based on the platform, and the key tests undertaken during system onsite commissioning.

IEEE Power and Energy MagazineVol. 23(2)
China Southern Power Grid (China) (CN)
Openalex Percentile: Top 97%
HVDC Systems and Fault Protection
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.