Analysis of Cost and Schedule Variances Using Earned Value Method on Waru - Buduran Frontage Road Bridge Construction Project

Infrastructure development is an important element in supporting economic growth, including in Indonesia. The Waru - Buduran Frontage Road Bridge development project was designed to overcome traffic congestion in the Sidoarjo area as a buffer zone for Surabaya. However, the project faced various obstacles, including schedule deviations and significant costs. This research aims to analyze the project's cost and schedule performance using the Earned Value Analysis method, focusing on Schedule Variance and Cost Variance to identify the main causes of delays and cost inefficiencies and provide recommendations for improvement. The research method used was a descriptive quantitative approach, with data collection through documentation of project financial reports, weekly schedules, and interviews with project managers. The analysis was carried out by calculating EVA indicators, such as Planned Value, Earned Value, and Actual Cost, to evaluate the cost efficiency and timeliness of the project. The results showed that the project experienced a negative schedule deviation of -9.911% in the 14th week, caused by technical constraints in utility relocation and coordination between stakeholders. However, the project still showed cost efficiency with a positive Cost Variance of 3.8%, indicating that actual costs were lower than the planned budget. The implications of this research highlight the need for more effective schedule planning, improved project coordination, and the implementation of acceleration strategies to reduce the impact of delays. In addition, the integration between schedule and cost management must be improved so that cost efficiency does not compromise the continuity of the project schedule.

Authors

Institutions

Publication Details

Journal
Asian Journal of Engineering Social and Health
Published
2025-02-22
DOI
https://doi.org/10.46799/ajesh.v4i2.528
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Cost and Schedule Variances Using Earned Value Method on Waru - Buduran Frontage Road Bridge Construction Project

Budi Witjaksana, Hanie Teki Tjendani, Suparno Suparno
Asian Journal of Engineering Social and Health
Management and Optimization Techniques
article

Analysis of Cost and Schedule Variances Using Earned Value Method on Waru - Buduran Frontage Road Bridge Construction Project

Budi Witjaksana, Hanie Teki Tjendani, Suparno Suparno
article en

Abstract

Infrastructure development is an important element in supporting economic growth, including in Indonesia. The Waru - Buduran Frontage Road Bridge development project was designed to overcome traffic congestion in the Sidoarjo area as a buffer zone for Surabaya. However, the project faced various obstacles, including schedule deviations and significant costs. This research aims to analyze the project's cost and schedule performance using the Earned Value Analysis method, focusing on Schedule Variance and Cost Variance to identify the main causes of delays and cost inefficiencies and provide recommendations for improvement. The research method used was a descriptive quantitative approach, with data collection through documentation of project financial reports, weekly schedules, and interviews with project managers. The analysis was carried out by calculating EVA indicators, such as Planned Value, Earned Value, and Actual Cost, to evaluate the cost efficiency and timeliness of the project. The results showed that the project experienced a negative schedule deviation of -9.911% in the 14th week, caused by technical constraints in utility relocation and coordination between stakeholders. However, the project still showed cost efficiency with a positive Cost Variance of 3.8%, indicating that actual costs were lower than the planned budget. The implications of this research highlight the need for more effective schedule planning, improved project coordination, and the implementation of acceleration strategies to reduce the impact of delays. In addition, the integration between schedule and cost management must be improved so that cost efficiency does not compromise the continuity of the project schedule.

Asian Journal of Engineering Social and HealthVol. 4(2)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 96%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis of Cost and Schedule Variances Using Earned Value Method on Waru - Buduran Frontage Road Bridge Construction Project — Budi Witjaksana, Hanie Teki Tjendani, et al. · Asian Journal of Engineering Social and Health (2025) | TGRS Research Map | TGRS