Tackling solar energy integration challenges on the Ireland and Northern Ireland power system

This paper discusses the upcoming challenges for the Ireland and Northern Ireland power system due to the significant integration of solar photovoltaic (PV). The Irish Government has set a target for 8 GW of solar capacity, both utility-scale and embedded, by 2030. The small island nature of the system, coupled with limited HVDC interconnections and an expected summer midday demand of 6.5 GW in 2030, presents considerable operational complexities. This paper identifies four potential challenges for the all-island power system: minimum operational demand, ramping effect, short-term variations, and post-fault behaviour. In 2030, with 2.5 GW of embedded PV capacity, sunny days may result in very low demand conditions, imposing challenges to maintain system stability. The paper also highlights potential ramping risks during daily load trends and rare events. Additionally, increasing short-term solar generation variations pose challenges like frequency fluctuations and voltage degradation. Post-fault distributed PV (DPV) tripping also poses risks for system security. This paper examines the risks and outlines recommendations for addressing these issues in light of the All-Island power system’s unique characteristics and developments.

Authors

Institutions

Publication Details

Journal
IET conference proceedings.
Published
2025-02-01
DOI
https://doi.org/10.1049/icp.2024.3909
Citations
1
Primary Topic
Renewable energy and sustainable power systems
Type
article
Field-Weighted Citation Impact
0.36
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Tackling solar energy integration challenges on the Ireland and Northern Ireland power system

Manuel Hurtado, Simon Tweed, Taulant Kërçi, Amir Moshari et al.
1 citations
IET conference proceedings.
Renewable energy and sustainable power systems
0.36
article

Tackling solar energy integration challenges on the Ireland and Northern Ireland power system

Manuel Hurtado, Simon Tweed, Taulant Kërçi, Amir Moshari, Eoin Kennedy, Saif Aldahmor
article en
1 citations

Abstract

This paper discusses the upcoming challenges for the Ireland and Northern Ireland power system due to the significant integration of solar photovoltaic (PV). The Irish Government has set a target for 8 GW of solar capacity, both utility-scale and embedded, by 2030. The small island nature of the system, coupled with limited HVDC interconnections and an expected summer midday demand of 6.5 GW in 2030, presents considerable operational complexities. This paper identifies four potential challenges for the all-island power system: minimum operational demand, ramping effect, short-term variations, and post-fault behaviour. In 2030, with 2.5 GW of embedded PV capacity, sunny days may result in very low demand conditions, imposing challenges to maintain system stability. The paper also highlights potential ramping risks during daily load trends and rare events. Additionally, increasing short-term solar generation variations pose challenges like frequency fluctuations and voltage degradation. Post-fault distributed PV (DPV) tripping also poses risks for system security. This paper examines the risks and outlines recommendations for addressing these issues in light of the All-Island power system’s unique characteristics and developments.

IET conference proceedings.Vol. 2024(16)
EirGrid (Ireland) (IE)
Affordable and clean energy
Openalex Percentile: Top 46%
Renewable energy and sustainable power systems
0.36
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Tackling solar energy integration challenges on the Ireland and Northern Ireland power system — Manuel Hurtado, Simon Tweed, et al. · IET conference proceedings. (2025) | TGRS Research Map | TGRS