Risk Factor Analysis on Contingency Costs of Phase I Wastewater Network Project in Bogor City

Contingency cost estimation is essential for construction project management to anticipate cost uncertainty due to various risks. This study analyzes risk-based contingency cost estimation in the Bogor City Phase I wastewater network system project. The background of this research is based on the need for accurate cost planning to avoid budget overruns and ensure project sustainability. The study aims to identify risk factors that affect contingency costs, group risks based on their degree of influence, and build a more accurate estimation model using the Partial Least Squares-Structural Equation Modeling (PLS-SEM) approach. This study uses a mixed method, namely qualitative analysis through interviews and literature studies to identify risk factors and a quantitative approach by distributing questionnaires to project stakeholders. The data was analyzed using SPSS 25 and SmartPLS software to test the validity and reliability of the contingency cost estimation model. The study results show that the most significant risk in the pre-construction stage is licensing and design, while in the construction stage is procuring equipment/materials and force majeure factors. The highest contingency cost estimate is in the preconstruction stage, with a value of 11.02%. The study's conclusion confirms that risk mitigation in the early stages of the project is essential to reduce the impact of budget uncertainty. The implications of this study contribute to the management of construction projects by providing a more accurate risk-based contingency cost estimation model that can be used as a reference for stakeholders in planning and managing infrastructure projects.

Authors

Institutions

Publication Details

Journal
Jurnal Indonesia Sosial Teknologi
Published
2025-02-22
DOI
https://doi.org/10.59141/jist.v6i2.8856
Primary Topic
Reliability and Maintenance Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Factor Analysis on Contingency Costs of Phase I Wastewater Network Project in Bogor City

Henny Pratiwi Adi, Doni Triatmojo, Hermin Poedjiastoeti
Jurnal Indonesia Sosial Teknologi
Reliability and Maintenance Optimization
article

Risk Factor Analysis on Contingency Costs of Phase I Wastewater Network Project in Bogor City

Henny Pratiwi Adi, Doni Triatmojo, Hermin Poedjiastoeti
article en

Abstract

Contingency cost estimation is essential for construction project management to anticipate cost uncertainty due to various risks. This study analyzes risk-based contingency cost estimation in the Bogor City Phase I wastewater network system project. The background of this research is based on the need for accurate cost planning to avoid budget overruns and ensure project sustainability. The study aims to identify risk factors that affect contingency costs, group risks based on their degree of influence, and build a more accurate estimation model using the Partial Least Squares-Structural Equation Modeling (PLS-SEM) approach. This study uses a mixed method, namely qualitative analysis through interviews and literature studies to identify risk factors and a quantitative approach by distributing questionnaires to project stakeholders. The data was analyzed using SPSS 25 and SmartPLS software to test the validity and reliability of the contingency cost estimation model. The study results show that the most significant risk in the pre-construction stage is licensing and design, while in the construction stage is procuring equipment/materials and force majeure factors. The highest contingency cost estimate is in the preconstruction stage, with a value of 11.02%. The study's conclusion confirms that risk mitigation in the early stages of the project is essential to reduce the impact of budget uncertainty. The implications of this study contribute to the management of construction projects by providing a more accurate risk-based contingency cost estimation model that can be used as a reference for stakeholders in planning and managing infrastructure projects.

Jurnal Indonesia Sosial TeknologiVol. 6(2)
Sultan Agung Islamic University (ID)
Openalex Percentile: Top 97%
Reliability and Maintenance Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.