Cost and Time Analysis Using The Earned Value Method In The Construction of Villa Kandya House, Ubud, Bali

In the Kandya House Villa Construction project in Ubud, Bali, there was a delay with a time deviation of -11.97%. This delay has the potential to cause the completion time of the work, which according to the contract is scheduled for 53 weeks, to be exceeded. To evaluate the time and cost performance in this project, the Earned Value method was used. This method utilizes three main indicators, namely Actual Cost of Work Performed (ACWP), Budgeted Cost of Work Performed (BCWP), and Budgeted Cost of Work Scheduled (BCWS). The results of the analysis show that the project time performance has decreased, characterized by a Schedule Variance (SV) value of -Rp 375,265,411.62. This value reflects a significant difference between planned and completed work. In addition, the Schedule Performance Index (SPI) was recorded at 0.772, which means that time efficiency only reached 77.2% of the planned schedule. As a result, the projected completion of work using the Estimate to Schedule (ETS) and Estimate at Schedule (EAS) indicators increased to 421 days or equivalent to 60.090 weeks, far exceeding the contract duration. In terms of cost, the analysis shows suboptimal performance, with a Cost Variance (CV) value of -Rp 48,700,590.06. This indicates that the actual costs incurred were higher than the planned budget for the completed work. In addition, the Cost Performance Index (CPI) value was recorded at 0.963, which means that the efficiency of budget utilization only reached 96.3%.

Authors

Institutions

Publication Details

Journal
Journal Of Social Research
Published
2025-02-22
DOI
https://doi.org/10.55324/josr.v4i3.2470
Primary Topic
Geotechnical and construction materials studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Cost and Time Analysis Using The Earned Value Method In The Construction of Villa Kandya House, Ubud, Bali

Jaka Purnama, Budi Witjaksana, Febri Cahyono
Journal Of Social Research
Geotechnical and construction materials studies
article

Cost and Time Analysis Using The Earned Value Method In The Construction of Villa Kandya House, Ubud, Bali

Jaka Purnama, Budi Witjaksana, Febri Cahyono
article en

Abstract

In the Kandya House Villa Construction project in Ubud, Bali, there was a delay with a time deviation of -11.97%. This delay has the potential to cause the completion time of the work, which according to the contract is scheduled for 53 weeks, to be exceeded. To evaluate the time and cost performance in this project, the Earned Value method was used. This method utilizes three main indicators, namely Actual Cost of Work Performed (ACWP), Budgeted Cost of Work Performed (BCWP), and Budgeted Cost of Work Scheduled (BCWS). The results of the analysis show that the project time performance has decreased, characterized by a Schedule Variance (SV) value of -Rp 375,265,411.62. This value reflects a significant difference between planned and completed work. In addition, the Schedule Performance Index (SPI) was recorded at 0.772, which means that time efficiency only reached 77.2% of the planned schedule. As a result, the projected completion of work using the Estimate to Schedule (ETS) and Estimate at Schedule (EAS) indicators increased to 421 days or equivalent to 60.090 weeks, far exceeding the contract duration. In terms of cost, the analysis shows suboptimal performance, with a Cost Variance (CV) value of -Rp 48,700,590.06. This indicates that the actual costs incurred were higher than the planned budget for the completed work. In addition, the Cost Performance Index (CPI) value was recorded at 0.963, which means that the efficiency of budget utilization only reached 96.3%.

Journal Of Social ResearchVol. 4(3)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 97%
Geotechnical and construction materials studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Cost and Time Analysis Using The Earned Value Method In The Construction of Villa Kandya House, Ubud, Bali — Jaka Purnama, Budi Witjaksana, et al. · Journal Of Social Research (2025) | TGRS Research Map | TGRS