Cost and Time Variance Analysis Using The Earned Value Method: A Case Study of The Laju Lor Village Drainage Channel Construction Project In Tuban Regency

This study aims to analyze the performance of the Drainage Development project in Laju Lor Village, Tuban District, using the Earned Value Management (EVM) method. The method integrates time and cost concepts through three main indicators: ACWP (Actual Cost of Work Performed), BCWP (Budgeted Cost of Work Performed), and BCWS (Budgeted Cost of Work Schedule). The research focuses on calculating Cost Variance (CV) and Schedule Variance (SV) to evaluate project performance. The method was applied to track the project's performance over a period of 5 weeks. In week 1, the project showed a delay of 0.38%, which increased to 4.84% by week 2. By the end of week 5, the results revealed that the Schedule Variance (SV) was Rp 74,378,242.82 (-), indicating that the project was behind schedule, while the Cost Variance (CV) was Rp 20,726,358.11 (+), showing that the costs incurred were less than the budgeted amount. The findings highlight the importance of using the Earned Value method to monitor project performance, ensuring that deviations in schedule and costs are promptly identified and addressed. The study concludes that implementing efficient control mechanisms and consistent supervision is essential for mitigating delays and improving project performance, specifically for the Laju Lor Village Drainage construction project in Tuban Regency. The research provides valuable insights for construction service providers to enhance project management practices and avoid further delays.

Authors

Institutions

Publication Details

Journal
Journal Of Social Research
Published
2025-02-22
DOI
https://doi.org/10.55324/josr.v4i3.2471
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Cost and Time Variance Analysis Using The Earned Value Method: A Case Study of The Laju Lor Village Drainage Channel Construction Project In Tuban Regency

Budi Witjaksana, Hanie Teki Tjendani, Utuh Dwi Candra Kelana Putra
Journal Of Social Research
Management and Optimization Techniques
article

Cost and Time Variance Analysis Using The Earned Value Method: A Case Study of The Laju Lor Village Drainage Channel Construction Project In Tuban Regency

Budi Witjaksana, Hanie Teki Tjendani, Utuh Dwi Candra Kelana Putra
article en

Abstract

This study aims to analyze the performance of the Drainage Development project in Laju Lor Village, Tuban District, using the Earned Value Management (EVM) method. The method integrates time and cost concepts through three main indicators: ACWP (Actual Cost of Work Performed), BCWP (Budgeted Cost of Work Performed), and BCWS (Budgeted Cost of Work Schedule). The research focuses on calculating Cost Variance (CV) and Schedule Variance (SV) to evaluate project performance. The method was applied to track the project's performance over a period of 5 weeks. In week 1, the project showed a delay of 0.38%, which increased to 4.84% by week 2. By the end of week 5, the results revealed that the Schedule Variance (SV) was Rp 74,378,242.82 (-), indicating that the project was behind schedule, while the Cost Variance (CV) was Rp 20,726,358.11 (+), showing that the costs incurred were less than the budgeted amount. The findings highlight the importance of using the Earned Value method to monitor project performance, ensuring that deviations in schedule and costs are promptly identified and addressed. The study concludes that implementing efficient control mechanisms and consistent supervision is essential for mitigating delays and improving project performance, specifically for the Laju Lor Village Drainage construction project in Tuban Regency. The research provides valuable insights for construction service providers to enhance project management practices and avoid further delays.

Journal Of Social ResearchVol. 4(3)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 96%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.