Limit Equilibrium Method of Slope Stability Analysis: A Case Study of Outlet Tunnel Portal of Bagong Dam East Java Indonesia

Abstract Bagong Dam, located in Trenggalek Regency, has a diversion tunnel. The diversion tunnel is designed as a horseshoe-type tunnel with a diameter of 4 m and a length of 416 m. Although a general engineering geological investigation has been conducted at the dam site, slope stability has yet to be analyzed. This research seeks to categorize rock masses based on the Geological Strength Index (GSI) and evaluate the stability of the slope at the tunnel outlet using the Bishop Simplified and Morgenstern-Price Limit Equilibrium Methods (LEM), considering scenarios with and without seismic load. The results will determine the appropriate slope for the tunnel outlet portal. The data for the LEM analysis were gathered through surface geological mapping, subsurface core sampling, and laboratory testing of the rock samples. The geological engineering of the Bagong Dam tunnel outlet consists of andesite breccia (fair to good), interbedded sandstone clay (poor to good), and poor-quality limestone. The horizontal seismic load coefficient (k h ) at this location is 0.175. LEM analysis shows that the portal slope is stable after excavation according to the design, static load shows a safety factor (Fs) = 2.16 > 1.5 using the Bishop Simplified and also shows a safety factor (Fs) = 2.15 > 1.5 using Morgenstren-Price. Post-seismic load analysis also shows a safety factor (Fs) = 1.94 > 1.1 using the Bishop Simplified and also shows a safety factor (Fs) = 1.89 > 1.1 using Morgenstren-Price. Slope failure does not occur because the safety factor values can be achieved using the original slope design, both with and without seismic load.

Authors

Institutions

Publication Details

Journal
IOP Conference Series Earth and Environmental Science
Published
2025-02-01
DOI
https://doi.org/10.1088/1755-1315/1451/1/012009
Primary Topic
Geotechnical Engineering and Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Limit Equilibrium Method of Slope Stability Analysis: A Case Study of Outlet Tunnel Portal of Bagong Dam East Java Indonesia

Rachmat Hidayat, I Gde Budi Indrawan, Sadewo Kusumo Digdoyo
IOP Conference Series Earth and Environmental Science
Geotechnical Engineering and Analysis
article

Limit Equilibrium Method of Slope Stability Analysis: A Case Study of Outlet Tunnel Portal of Bagong Dam East Java Indonesia

Rachmat Hidayat, I Gde Budi Indrawan, Sadewo Kusumo Digdoyo
article en

Abstract

Abstract Bagong Dam, located in Trenggalek Regency, has a diversion tunnel. The diversion tunnel is designed as a horseshoe-type tunnel with a diameter of 4 m and a length of 416 m. Although a general engineering geological investigation has been conducted at the dam site, slope stability has yet to be analyzed. This research seeks to categorize rock masses based on the Geological Strength Index (GSI) and evaluate the stability of the slope at the tunnel outlet using the Bishop Simplified and Morgenstern-Price Limit Equilibrium Methods (LEM), considering scenarios with and without seismic load. The results will determine the appropriate slope for the tunnel outlet portal. The data for the LEM analysis were gathered through surface geological mapping, subsurface core sampling, and laboratory testing of the rock samples. The geological engineering of the Bagong Dam tunnel outlet consists of andesite breccia (fair to good), interbedded sandstone clay (poor to good), and poor-quality limestone. The horizontal seismic load coefficient (k h ) at this location is 0.175. LEM analysis shows that the portal slope is stable after excavation according to the design, static load shows a safety factor (Fs) = 2.16 > 1.5 using the Bishop Simplified and also shows a safety factor (Fs) = 2.15 > 1.5 using Morgenstren-Price. Post-seismic load analysis also shows a safety factor (Fs) = 1.94 > 1.1 using the Bishop Simplified and also shows a safety factor (Fs) = 1.89 > 1.1 using Morgenstren-Price. Slope failure does not occur because the safety factor values can be achieved using the original slope design, both with and without seismic load.

IOP Conference Series Earth and Environmental ScienceVol. 1451(1)
Universitas Gadjah Mada (ID)
Openalex Percentile: Top 91%
Geotechnical Engineering and Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Limit Equilibrium Method of Slope Stability Analysis: A Case Study of Outlet Tunnel Portal of Bagong Dam East Java Indonesia — Rachmat Hidayat, I Gde Budi Indrawan, et al. · IOP Conference Series Earth and Environmental Science (2025) | TGRS Research Map | TGRS