PERBANDINGAN METODE EARNED SCHEDULE DAN EARNED VALUE DALAM PENGONTROLAN PROYEK PADA ASPEK WAKTU

Project management success entails effectively managing project performance, progress, and costs. One method that integrates cost, time, and performance aspects is Earned Value (EV). As an evolution of EV, a new method called Earned Schedule (ES) has emerged. Typically, projects experience planned delays, both in terms of time and progress. The purpose of performance analysis using these two methods is to evaluate performance achievement during project implementation and to understand the extent of deviations that may occur in the work. In completing this analysis, the first step is to obtain values ​​from various indicators needed in each project review. From the project 1 analysis results, because the project progresses as planned, which is 16 weeks, the EV method shows delays every week in terms of cost and time aspects. The ES method can demonstrate the duration of delay every week in terms of time aspect, unlike project 2, based on the project 2 data calculation, the ES method excels because in the ES method the SPI(t) value can indicate delays in the last week of the project, as evidenced by the SPI(t) value in week 18 of 0.8888, whereas in the EV method, the SPI value in the last week is 1. The Earned Schedule method excels in project monitoring, especially in projects experiencing delays. Abstrak Keberhasilan dalam manajemen proyek melibatkan pengelolaan kinerja, progres, dan biaya proyek secara efektif. Salah satu metode yang mengintegrasikan aspek biaya, waktu, dan kinerja adalah Earned Value (EV). Sebagai perkembangan dari EV, ada metode baru yang dikenal sebagai Earned Schedule (ES). Umumnya, proyek akan mengalami penundaan yang sudah diantisipasi, baik dalam hal waktu maupun kemajuan pekerjaan. Analisis kinerja menggunakan kedua metode ini bertujuan untuk mengevaluasi pencapaian kinerja selama pelaksanaan proyek dan memahami sejauh mana penyimpangan yang mungkin terjadi dalam pekerjaan tersebut. Dalam menyelesaikan analisis ini, langkah pertama adalah memperoleh nilai dari berbagai indikator yang diperlukan pada setiap tinjauan proyek, dari hasil analisis proyek 1, karena proyek berjalan sesuai dengan rencananya yaitu 16 minggu, metode EV menunjukkan keterlambatan setiap minggu dalam aspek biaya dan waktu. Metode ES dapat memperlihatkan durasi keterlambatan setiap minggunya dalam aspek waktu, berbeda dengan proyek 2, berdasarkan perhitungan data proyek 2, metode ES unggul karena pada metode ES nilai SPI(t) dapat menunjukkan keterlambatan di minggu akhir proyek yang dibuktikan dengan nilai SPI(t) di minggu ke-18 sebesar 0.8888, sedangkan pada metode EV, nilai SPI pada minggu akhir sebesar 1. Metode Earned Schedule unggul dalam pemantauan proyek khususnya pada proyek yang mengalami keterlambatan.

Authors

Institutions

Publication Details

Journal
JMTS Jurnal Mitra Teknik Sipil
Published
2025-02-18
DOI
https://doi.org/10.24912/jmts.v8i1.30381
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

PERBANDINGAN METODE EARNED SCHEDULE DAN EARNED VALUE DALAM PENGONTROLAN PROYEK PADA ASPEK WAKTU

Daniel Nathan Iskandar, Fuk Jin Oei
JMTS Jurnal Mitra Teknik Sipil
Management and Optimization Techniques
article

PERBANDINGAN METODE EARNED SCHEDULE DAN EARNED VALUE DALAM PENGONTROLAN PROYEK PADA ASPEK WAKTU

Daniel Nathan Iskandar, Fuk Jin Oei
article en

Abstract

Project management success entails effectively managing project performance, progress, and costs. One method that integrates cost, time, and performance aspects is Earned Value (EV). As an evolution of EV, a new method called Earned Schedule (ES) has emerged. Typically, projects experience planned delays, both in terms of time and progress. The purpose of performance analysis using these two methods is to evaluate performance achievement during project implementation and to understand the extent of deviations that may occur in the work. In completing this analysis, the first step is to obtain values ​​from various indicators needed in each project review. From the project 1 analysis results, because the project progresses as planned, which is 16 weeks, the EV method shows delays every week in terms of cost and time aspects. The ES method can demonstrate the duration of delay every week in terms of time aspect, unlike project 2, based on the project 2 data calculation, the ES method excels because in the ES method the SPI(t) value can indicate delays in the last week of the project, as evidenced by the SPI(t) value in week 18 of 0.8888, whereas in the EV method, the SPI value in the last week is 1. The Earned Schedule method excels in project monitoring, especially in projects experiencing delays. Abstrak Keberhasilan dalam manajemen proyek melibatkan pengelolaan kinerja, progres, dan biaya proyek secara efektif. Salah satu metode yang mengintegrasikan aspek biaya, waktu, dan kinerja adalah Earned Value (EV). Sebagai perkembangan dari EV, ada metode baru yang dikenal sebagai Earned Schedule (ES). Umumnya, proyek akan mengalami penundaan yang sudah diantisipasi, baik dalam hal waktu maupun kemajuan pekerjaan. Analisis kinerja menggunakan kedua metode ini bertujuan untuk mengevaluasi pencapaian kinerja selama pelaksanaan proyek dan memahami sejauh mana penyimpangan yang mungkin terjadi dalam pekerjaan tersebut. Dalam menyelesaikan analisis ini, langkah pertama adalah memperoleh nilai dari berbagai indikator yang diperlukan pada setiap tinjauan proyek, dari hasil analisis proyek 1, karena proyek berjalan sesuai dengan rencananya yaitu 16 minggu, metode EV menunjukkan keterlambatan setiap minggu dalam aspek biaya dan waktu. Metode ES dapat memperlihatkan durasi keterlambatan setiap minggunya dalam aspek waktu, berbeda dengan proyek 2, berdasarkan perhitungan data proyek 2, metode ES unggul karena pada metode ES nilai SPI(t) dapat menunjukkan keterlambatan di minggu akhir proyek yang dibuktikan dengan nilai SPI(t) di minggu ke-18 sebesar 0.8888, sedangkan pada metode EV, nilai SPI pada minggu akhir sebesar 1. Metode Earned Schedule unggul dalam pemantauan proyek khususnya pada proyek yang mengalami keterlambatan.

JMTS Jurnal Mitra Teknik Sipil
Tarumanagara University (ID)
Openalex Percentile: Top 96%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.