ANALISIS PENYEBAB KETERLAMBATAN PADA PROYEK X DI SLIPI MENGGUNAKAN METODE RELATIVE IMPORTANCE INDEX (RII)

One of the important variables that determine the success of a construction project is the duration of said project. There are many factors that can negatively affect a project’s duration, from design to finishing, causing delays in the long term. This study aims to identify and determine the highest ranking of delay factors in a high-rise building project. In this study, data is obtained quantitatively by distributing questionnaires to the construction actors of Project X in Slipi, West Jakarta. Analysis of the data’s validity and reliability is conducted using the IBM SPSS (Statistical Package for the Social Sciences) software, and the significance of each variable is determined with the RII (Relative Importance Index) method using Microsoft Excel. 12 out of 20 variables in this study are deemed valid and reliable according to the analysis results. Out of those 12 factors, the highest ranking of delay factors in Project X is inadequate site management, with an RII score of 0.7292. Abstrak Salah satu variabel penting yang menentukan keberhasilan suatu proyek konstruksi adalah durasi dari pelaksanaan proyek tersebut. Terdapat banyak faktor yang dapat mempengaruhi durasi proyek secara negatif, mulai dari desain hingga penyelesaian, sehingga mengakibatkan keterlambatan dalam jangka panjang. Studi ini bertujuan untuk mengidentifikasi dan menentukan peringkat tertinggi faktor-faktor keterlambatan dalam proyek gedung bertingkat tinggi. Dalam studi ini, data diperoleh secara kuantitatif dengan menyebarkan kuesioner pada pelaku konstruksi Proyek X di Slipi, Jakarta Barat. Analisis terhadap validitas dan reliabilitas data dilakukan menggunakan perangkat lunak IBM SPSS (Statistical Package for the Social Sciences), dan signifikansi masing-masing variabel ditentukan dengan metode RII (relative importance index) menggunakan Microsoft Excel. 12 dari 20 variabel dalam studi ini dianggap valid dan reliabel berdasarkan hasil analisis. Dari 12 faktor tersebut, peringkat tertinggi dari faktor keterlambatan di Proyek X adalah site management yang kurang baik, dengan skor RII sebesar 0,7292.

Authors

Institutions

Publication Details

Journal
JMTS Jurnal Mitra Teknik Sipil
Published
2025-02-18
DOI
https://doi.org/10.24912/jmts.v8i1.33263
Citations
1
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
2.23
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS PENYEBAB KETERLAMBATAN PADA PROYEK X DI SLIPI MENGGUNAKAN METODE RELATIVE IMPORTANCE INDEX (RII)

Arif Sandjaya, Jason Christian Sukma
1 citations
JMTS Jurnal Mitra Teknik Sipil
Management and Optimization Techniques
2.23
article

ANALISIS PENYEBAB KETERLAMBATAN PADA PROYEK X DI SLIPI MENGGUNAKAN METODE RELATIVE IMPORTANCE INDEX (RII)

Arif Sandjaya, Jason Christian Sukma
article en
1 citations

Abstract

One of the important variables that determine the success of a construction project is the duration of said project. There are many factors that can negatively affect a project’s duration, from design to finishing, causing delays in the long term. This study aims to identify and determine the highest ranking of delay factors in a high-rise building project. In this study, data is obtained quantitatively by distributing questionnaires to the construction actors of Project X in Slipi, West Jakarta. Analysis of the data’s validity and reliability is conducted using the IBM SPSS (Statistical Package for the Social Sciences) software, and the significance of each variable is determined with the RII (Relative Importance Index) method using Microsoft Excel. 12 out of 20 variables in this study are deemed valid and reliable according to the analysis results. Out of those 12 factors, the highest ranking of delay factors in Project X is inadequate site management, with an RII score of 0.7292. Abstrak Salah satu variabel penting yang menentukan keberhasilan suatu proyek konstruksi adalah durasi dari pelaksanaan proyek tersebut. Terdapat banyak faktor yang dapat mempengaruhi durasi proyek secara negatif, mulai dari desain hingga penyelesaian, sehingga mengakibatkan keterlambatan dalam jangka panjang. Studi ini bertujuan untuk mengidentifikasi dan menentukan peringkat tertinggi faktor-faktor keterlambatan dalam proyek gedung bertingkat tinggi. Dalam studi ini, data diperoleh secara kuantitatif dengan menyebarkan kuesioner pada pelaku konstruksi Proyek X di Slipi, Jakarta Barat. Analisis terhadap validitas dan reliabilitas data dilakukan menggunakan perangkat lunak IBM SPSS (Statistical Package for the Social Sciences), dan signifikansi masing-masing variabel ditentukan dengan metode RII (relative importance index) menggunakan Microsoft Excel. 12 dari 20 variabel dalam studi ini dianggap valid dan reliabel berdasarkan hasil analisis. Dari 12 faktor tersebut, peringkat tertinggi dari faktor keterlambatan di Proyek X adalah site management yang kurang baik, dengan skor RII sebesar 0,7292.

JMTS Jurnal Mitra Teknik Sipil
Tarumanagara University (ID)
Openalex Percentile: Top 13%
Management and Optimization Techniques
2.23
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.