Analysis of Project Time Using the Earned Value Method Concept on the Situbondo District Bagor Bridge Replacement Project

This research aims to analyze the time and cost efficiency of the Bagor Bridge Replacement Project in Situbondo Regency using the Earned Value Method. The research employs a qualitative descriptive approach, where data is collected through literature studies, field observations, and analysis of project documents such as plan drawings and weekly reports. Data analysis techniques include calculating several indicators, including Cost Performance Index (CPI), Schedule Performance Index (SPI), and Variance at Completion (VAC). The results showed that in weeks one to nine, the project ran according to the planned schedule, but there was a delay between weeks ten to nineteen. In the twentieth to twenty-fourth week, the project made progress again. The effectiveness of project time and cost control was obtained with a score value of 1.603, which indicates that project control is very effective. Based on these results, it is recommended that the implementing contractor compile detailed daily reports to monitor cost overruns and anticipate existing risks. The use of Earned Value method can be combined with other methods to maximize project control. In addition, logistics, equipment, and resource management should be considered to prevent unwanted problems.

Authors

Institutions

Publication Details

Journal
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)
Published
2025-01-28
DOI
https://doi.org/10.55047/ijateis.v4i1.1575
Citations
1
Primary Topic
Value Engineering and Management
Type
article
Field-Weighted Citation Impact
2.23
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Project Time Using the Earned Value Method Concept on the Situbondo District Bagor Bridge Replacement Project

Sajiyo Sajiyo, Andi Patriadi, Yonandika Pandu Putranto
1 citations
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)
Value Engineering and Management
2.23
article

Analysis of Project Time Using the Earned Value Method Concept on the Situbondo District Bagor Bridge Replacement Project

Sajiyo Sajiyo, Andi Patriadi, Yonandika Pandu Putranto
article en
1 citations

Abstract

This research aims to analyze the time and cost efficiency of the Bagor Bridge Replacement Project in Situbondo Regency using the Earned Value Method. The research employs a qualitative descriptive approach, where data is collected through literature studies, field observations, and analysis of project documents such as plan drawings and weekly reports. Data analysis techniques include calculating several indicators, including Cost Performance Index (CPI), Schedule Performance Index (SPI), and Variance at Completion (VAC). The results showed that in weeks one to nine, the project ran according to the planned schedule, but there was a delay between weeks ten to nineteen. In the twentieth to twenty-fourth week, the project made progress again. The effectiveness of project time and cost control was obtained with a score value of 1.603, which indicates that project control is very effective. Based on these results, it is recommended that the implementing contractor compile detailed daily reports to monitor cost overruns and anticipate existing risks. The use of Earned Value method can be combined with other methods to maximize project control. In addition, logistics, equipment, and resource management should be considered to prevent unwanted problems.

INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)Vol. 4(1)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 13%
Value Engineering and Management
2.23
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis of Project Time Using the Earned Value Method Concept on the Situbondo District Bagor Bridge Replacement Project — Sajiyo Sajiyo, Andi Patriadi, et al. · INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS) (2025) | TGRS Research Map | TGRS