TIME DELAY ANALYSIS USING CRITICAL PATH METHOD (CPM) (Case Study: Kerobokan Bali Parking Building Construction Project)

Parking Building is a structure specifically built for vehicle parking. Kerobokan Bali Parking Building is one such structure that utilizes steel as its main material. With dimensions of 13.97 meters in height, 32.8 meters in width, and 16.18 meters in length, this building had a planned construction duration of 259 calendar days starting from July 2023. The parking building experienced delays due to flooding in the basement area, necessitating time acceleration analysis using the CPM method. This thesis employs the CPM method to identify critical path activities. Once the critical paths are identified, a crashing program analysis will be conducted, involving an alternative such as overtime work with a duration of 4 hours. Based on the analysis using the CPM method, it was found that 75 activities are critical, listed in Microsoft Project rows 368-369-370-372-380-381-382-383-384-385-387-388-389-390-392-393-394-395-398-399-400-402-403-404-406-412-415-416-417-419-420-421-422-424-425-426-427-428-430-431-432-433-435-436-437-438-441-442-443-445-471-472-473-475-476-477-479-526-527-528-530-535-621-628-629-630-633-634-635-638-639-640-643-644.

Authors

Institutions

Publication Details

Journal
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)
Published
2024-09-04
DOI
https://doi.org/10.55047/ijateis.v3i4.1189
Primary Topic
Decision Support System Applications
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

TIME DELAY ANALYSIS USING CRITICAL PATH METHOD (CPM) (Case Study: Kerobokan Bali Parking Building Construction Project)

Budi Witjaksana, Hanie Teki Tjendani, Dwi Cahyani Putri
INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)
Decision Support System Applications
article

TIME DELAY ANALYSIS USING CRITICAL PATH METHOD (CPM) (Case Study: Kerobokan Bali Parking Building Construction Project)

Budi Witjaksana, Hanie Teki Tjendani, Dwi Cahyani Putri
article en

Abstract

Parking Building is a structure specifically built for vehicle parking. Kerobokan Bali Parking Building is one such structure that utilizes steel as its main material. With dimensions of 13.97 meters in height, 32.8 meters in width, and 16.18 meters in length, this building had a planned construction duration of 259 calendar days starting from July 2023. The parking building experienced delays due to flooding in the basement area, necessitating time acceleration analysis using the CPM method. This thesis employs the CPM method to identify critical path activities. Once the critical paths are identified, a crashing program analysis will be conducted, involving an alternative such as overtime work with a duration of 4 hours. Based on the analysis using the CPM method, it was found that 75 activities are critical, listed in Microsoft Project rows 368-369-370-372-380-381-382-383-384-385-387-388-389-390-392-393-394-395-398-399-400-402-403-404-406-412-415-416-417-419-420-421-422-424-425-426-427-428-430-431-432-433-435-436-437-438-441-442-443-445-471-472-473-475-476-477-479-526-527-528-530-535-621-628-629-630-633-634-635-638-639-640-643-644.

INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)Vol. 3(4)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 57%
Decision Support System Applications
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

TIME DELAY ANALYSIS USING CRITICAL PATH METHOD (CPM) (Case Study: Kerobokan Bali Parking Building Construction Project) — Budi Witjaksana, Hanie Teki Tjendani, et al. · INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS) (2024) | TGRS Research Map | TGRS