Analysis and Suggestions for a 220 kV GIS Trip Fault

GIS has significant advantages such as small footprint, strong pollution resistance, easy installation, and flexible operation, and is widely used in urban substations of 72.5kV and above in China. However, due to the lack of experience in the operation of fully enclosed electrical appliances in China, the testing items in the manufacturing and installation process are not complete enough, which may lead to unforeseen hidden dangers in actual use. This article analyzes the causes of an accident caused by the loosening of the fixing bolts between the contact and the contact seat in the busbar interval, during the operation of a 220 kV GIS, resulting in contact finger erosion, shell breakdown, and three phases grounding faults. Simulation methods are used to conduct simulation tests of the fault process. Feasible suggestions are proposed for identifying potential hazards of similar problems.

Authors

Institutions

Publication Details

Published
2024-11-28
DOI
https://doi.org/10.1109/ispcem64498.2024.00118
Citations
1
Primary Topic
Power Systems and Technologies
Type
article
Field-Weighted Citation Impact
0.21
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis and Suggestions for a 220 kV GIS Trip Fault

Limin Qu, Weinan Gao, Yubo Shen, Xiaoguang Ma et al.
1 citations
Power Systems and Technologies
0.21
article

Analysis and Suggestions for a 220 kV GIS Trip Fault

Limin Qu, Weinan Gao, Yubo Shen, Xiaoguang Ma, Siwei Han, Wenhao Li, Xueting Wang, Ke Wang, Hongyi Zhou
article en
1 citations

Abstract

GIS has significant advantages such as small footprint, strong pollution resistance, easy installation, and flexible operation, and is widely used in urban substations of 72.5kV and above in China. However, due to the lack of experience in the operation of fully enclosed electrical appliances in China, the testing items in the manufacturing and installation process are not complete enough, which may lead to unforeseen hidden dangers in actual use. This article analyzes the causes of an accident caused by the loosening of the fixing bolts between the contact and the contact seat in the busbar interval, during the operation of a 220 kV GIS, resulting in contact finger erosion, shell breakdown, and three phases grounding faults. Simulation methods are used to conduct simulation tests of the fault process. Feasible suggestions are proposed for identifying potential hazards of similar problems.

Harbin Electric Corporation (China) (CN)
Climate action
Openalex Percentile: Top 44%
Power Systems and Technologies
0.21
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.