Risk Assessment with Monte Carlo Simulation to Improve Bridge Construction Safety

The safety of bridge construction has become a special concern for the Indonesian government since many bridge construction accidents occurred in 2017 and 2018. Construction projects involve a small number of contractor employees, so when conducting accident risk assessments, the results become less accurate. Monte Carlo simulation is a method that can be applied to conduct risk analysis with limited available data. This research began with the identification of potential risks that might occur in bridge construction, resulting in 24 types of risks. Risk assessment was conducted based on the list of risks identified by the contractor’s employees who were working on a bridge project. The results of the risk assessment were then analyzed and prepared for the Monte Carlo simulation process. The simulation results showed accurate outcomes with a total of 10,000 simulations. The greatest risks occur when a worker falls, which has a risk index of 12.5961, and a girder collapses during installation, which has a risk index of 16.1873.

Authors

Institutions

Publication Details

Published
2025-02-12
DOI
https://doi.org/10.3390/engproc2025084056
Citations
4
Primary Topic
Infrastructure Maintenance and Monitoring
Type
article
Field-Weighted Citation Impact
2.86
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Assessment with Monte Carlo Simulation to Improve Bridge Construction Safety

Wahyudi Sutopo, Dewi Handayani, Widi Hartono, Stefanus Adi Kristiawan
4 citations
Infrastructure Maintenance and Monitoring
2.86
article

Risk Assessment with Monte Carlo Simulation to Improve Bridge Construction Safety

Wahyudi Sutopo, Dewi Handayani, Widi Hartono, Stefanus Adi Kristiawan
article en
4 citations

Abstract

The safety of bridge construction has become a special concern for the Indonesian government since many bridge construction accidents occurred in 2017 and 2018. Construction projects involve a small number of contractor employees, so when conducting accident risk assessments, the results become less accurate. Monte Carlo simulation is a method that can be applied to conduct risk analysis with limited available data. This research began with the identification of potential risks that might occur in bridge construction, resulting in 24 types of risks. Risk assessment was conducted based on the list of risks identified by the contractor’s employees who were working on a bridge project. The results of the risk assessment were then analyzed and prepared for the Monte Carlo simulation process. The simulation results showed accurate outcomes with a total of 10,000 simulations. The greatest risks occur when a worker falls, which has a risk index of 12.5961, and a girder collapses during installation, which has a risk index of 16.1873.

Sebelas Maret University (ID)
Openalex Percentile: Top 12%
Infrastructure Maintenance and Monitoring
2.86
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.