Data Augmentation Approaches for Estimating Curtain Wall Construction Duration in High-Rise Buildings

Reliable project management during planning stages of a building project is a meticulous process typically requiring sufficient precedencies. Typical construction duration estimation is based on previous cases of similar projects used to validate construction duration proposals from contractors, plan overall project duration, and set a standard for project success or failure. In cases of high-rise buildings exceeding 200 m, insufficient data commonly arise from the rarity of such projects, leading to a rough estimation of construction duration. Therefore, in this study, oversampling and data augmentation techniques derived from engineering principles, such as parametric optimization and data imbalance problems, are explored for curtain wall construction for high-rise buildings. The study was conducted in two phases. First, oversampling and data augmentation techniques, including Latin Hypercube, optimal Latin Hypercube, simple Monte Carlo, descriptive Monte Carlo, Sobol Monte Carlo, synthetic minority oversampling technique (SMOTE), and SMOTE–Tomek, were applied to 15 raw datasets collected from previous projects. The dataset was split into 8:2 for training and testing, where the mentioned techniques were applied to generate 500 virtual samples from the training data. Second, support vector regression was applied to forecast construction duration, where statistical performance criteria were applied for evaluation. The results showed that SMOTE and SMOTE–Tomek best represented the original dataset based on box plot analysis showcasing data distribution. Moreover, according to statistical performance criteria, it was found that the oversampling techniques improved the prediction performance, where Pearson correlation for linear, polynomial, and RBF increased by 0.611%, 4.232%, and 0.594%, respectively, for the best-performing sampling method. Finally, for the prediction models, probabilistic oversampling methods outperformed other methods according to the statistical performance criteria.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-02-13
DOI
https://doi.org/10.3390/buildings15040583
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Data Augmentation Approaches for Estimating Curtain Wall Construction Duration in High-Rise Buildings

Jin-Bin Im, Ju-Hyung Kim, Sang-Jun Park, H.K. Yoon
Buildings
BIM and Construction Integration
article

Data Augmentation Approaches for Estimating Curtain Wall Construction Duration in High-Rise Buildings

Jin-Bin Im, Ju-Hyung Kim, Sang-Jun Park, H.K. Yoon
article en

Abstract

Reliable project management during planning stages of a building project is a meticulous process typically requiring sufficient precedencies. Typical construction duration estimation is based on previous cases of similar projects used to validate construction duration proposals from contractors, plan overall project duration, and set a standard for project success or failure. In cases of high-rise buildings exceeding 200 m, insufficient data commonly arise from the rarity of such projects, leading to a rough estimation of construction duration. Therefore, in this study, oversampling and data augmentation techniques derived from engineering principles, such as parametric optimization and data imbalance problems, are explored for curtain wall construction for high-rise buildings. The study was conducted in two phases. First, oversampling and data augmentation techniques, including Latin Hypercube, optimal Latin Hypercube, simple Monte Carlo, descriptive Monte Carlo, Sobol Monte Carlo, synthetic minority oversampling technique (SMOTE), and SMOTE–Tomek, were applied to 15 raw datasets collected from previous projects. The dataset was split into 8:2 for training and testing, where the mentioned techniques were applied to generate 500 virtual samples from the training data. Second, support vector regression was applied to forecast construction duration, where statistical performance criteria were applied for evaluation. The results showed that SMOTE and SMOTE–Tomek best represented the original dataset based on box plot analysis showcasing data distribution. Moreover, according to statistical performance criteria, it was found that the oversampling techniques improved the prediction performance, where Pearson correlation for linear, polynomial, and RBF increased by 0.611%, 4.232%, and 0.594%, respectively, for the best-performing sampling method. Finally, for the prediction models, probabilistic oversampling methods outperformed other methods according to the statistical performance criteria.

BuildingsVol. 15(4)
Hanyang University (KR), Anyang University (KR)
Openalex Percentile: Top 98%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.