Determining Cost-Efficient Sequence of Condition Inspection Based on Estimated Condition Data

This paper presents a methodology to determine the cost-efficient sequence of substation equipment inspections. It is mainly intended for cases when having limited or absent data about equipment condition. The methodology is based on the usage of known condition data to estimate the condition of equipment with unknown data. It is estimated by fitting the likelihood function to the distribution of known Health Index values of equipment. The estimation values are implemented as an input to determine the cost-efficient sequence of equipment inspections. As a result, the process allows to decrease the uncertainty in condition data, avoid costly failures, and reduce total inspection cost. The methodology is tested on the IEEE 39-bus power system. The obtained results indicated the reduction of inspection cost by 80 % in the example case and avoiding failures with higher cost. The process can assist in risk reduction when having equipment with unknown or limited condition data.

Authors

Institutions

Publication Details

Published
2024-10-14
DOI
https://doi.org/10.1109/isgteurope62998.2024.10863436
Primary Topic
Engineering Diagnostics and Reliability
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Determining Cost-Efficient Sequence of Condition Inspection Based on Estimated Condition Data

Madis Leinakse, Guido Andreesen, Jako Kilter, Mart Landsberg
Engineering Diagnostics and Reliability
article

Determining Cost-Efficient Sequence of Condition Inspection Based on Estimated Condition Data

Madis Leinakse, Guido Andreesen, Jako Kilter, Mart Landsberg
article en

Abstract

This paper presents a methodology to determine the cost-efficient sequence of substation equipment inspections. It is mainly intended for cases when having limited or absent data about equipment condition. The methodology is based on the usage of known condition data to estimate the condition of equipment with unknown data. It is estimated by fitting the likelihood function to the distribution of known Health Index values of equipment. The estimation values are implemented as an input to determine the cost-efficient sequence of equipment inspections. As a result, the process allows to decrease the uncertainty in condition data, avoid costly failures, and reduce total inspection cost. The methodology is tested on the IEEE 39-bus power system. The obtained results indicated the reduction of inspection cost by 80 % in the example case and avoiding failures with higher cost. The process can assist in risk reduction when having equipment with unknown or limited condition data.

Tallinn University of Technology (EE)
Openalex Percentile: Top 70%
Engineering Diagnostics and Reliability
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.