Analysis of PVD Installation Methods Due to Limited Vertical Clearance in the Lamongan North Ring Road Construction Project Section 1 STA 0+400 to STA 0+426

The construction of the Lamongan North Ring Road is planned to be built on soft soil. Based on the results of the soil investigation, it is known that the subgrade condition is classified as soft to very soft soil with a depth of 18 meters. One of the problems of this very soft soil is the settlement. Therefore, the National Road Implementation Agency of East Java - Bali Region conducted subgrade improvement using preloading combined with Prefabricated Vertical Drain (PVD). The configuration of the PVD installation is 18 meters deep with a triangular pattern and the distance between PVDs is 1 meter. To stake the PVDs 18 meters deep, a piling rig with a minimum height of 24 meters is required. In the STA 0+400 to STA 0+426 section there is a 150 kV Lamongan - Paciran High Voltage Air Line (SUTT) cable crossing the road with a conductor to platform distance of 18 meters. The existence of this cable is a challenge in the PVD driving as deep as 18 meters. Therefore, this journal will analyze the PVD piling implementation method that can be carried out in this segment. The method carried out in this study is to start with the collection of secondary data such as shop drawings as a reference for the implementation of work in accordance with the planned design. Based on the design plan, an implementation method that can be applied to limited vertical clearance conditions is obtained. Based on the results of the research, an 18-meter deep PVD installation method was obtained that can be applied to limited vertical clearance conditions in the Lamongan North Ring Road construction project Section 1 STA 0+400 to STA 0+426. In addition, it was also found that the time required was 34.75 minutes to stake 1 PVD point using the pulled hole PVD method.

Authors

Institutions

Publication Details

Journal
Journal of Infrastructure & Facility Asset Management
Published
2025-01-28
DOI
https://doi.org/10.12962/jifam.v7i0.22485
Primary Topic
Structural Engineering and Vibration Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of PVD Installation Methods Due to Limited Vertical Clearance in the Lamongan North Ring Road Construction Project Section 1 STA 0+400 to STA 0+426

Yudhi Lastiasih, Herman Wahyudi, Fanny Rumintha Br Barimbing, Sifa` Udukha
Journal of Infrastructure & Facility Asset Management
Structural Engineering and Vibration Analysis
article

Analysis of PVD Installation Methods Due to Limited Vertical Clearance in the Lamongan North Ring Road Construction Project Section 1 STA 0+400 to STA 0+426

Yudhi Lastiasih, Herman Wahyudi, Fanny Rumintha Br Barimbing, Sifa` Udukha
article en

Abstract

The construction of the Lamongan North Ring Road is planned to be built on soft soil. Based on the results of the soil investigation, it is known that the subgrade condition is classified as soft to very soft soil with a depth of 18 meters. One of the problems of this very soft soil is the settlement. Therefore, the National Road Implementation Agency of East Java - Bali Region conducted subgrade improvement using preloading combined with Prefabricated Vertical Drain (PVD). The configuration of the PVD installation is 18 meters deep with a triangular pattern and the distance between PVDs is 1 meter. To stake the PVDs 18 meters deep, a piling rig with a minimum height of 24 meters is required. In the STA 0+400 to STA 0+426 section there is a 150 kV Lamongan - Paciran High Voltage Air Line (SUTT) cable crossing the road with a conductor to platform distance of 18 meters. The existence of this cable is a challenge in the PVD driving as deep as 18 meters. Therefore, this journal will analyze the PVD piling implementation method that can be carried out in this segment. The method carried out in this study is to start with the collection of secondary data such as shop drawings as a reference for the implementation of work in accordance with the planned design. Based on the design plan, an implementation method that can be applied to limited vertical clearance conditions is obtained. Based on the results of the research, an 18-meter deep PVD installation method was obtained that can be applied to limited vertical clearance conditions in the Lamongan North Ring Road construction project Section 1 STA 0+400 to STA 0+426. In addition, it was also found that the time required was 34.75 minutes to stake 1 PVD point using the pulled hole PVD method.

Journal of Infrastructure & Facility Asset ManagementVol. 7(0)
Sepuluh Nopember Institute of Technology (ID), National Nuclear Energy Agency of Indonesia (ID)
Sustainable cities and communities
Openalex Percentile: Top 97%
Structural Engineering and Vibration Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.