Analysis of Temporary Preloading for Bridge Approach Embankment to Eliminate Secondary Compression Case Study: Probolinggo – Banyuwangi Toll Road Construction Project Section 3 STA 40+550

Probolinggo - Banyuwangi Toll Road is part of the National Strategic Project, has a length of 172 km which is divided into 7 sections. One of the challenges faced is soft soil, where information is obtained in section 3 precisely STA 40 + 550 there is soft soil, which has low bearing capacity and high compressibility. The depth of the soft soil itself reaches 10 meters, with the plan to build in the approach bridge area which has a 10 meter high embankment. Considering the high embankment, based on previous studies, it is estimated that the amount of primary and secondary compression generated is quite large. This study analyzes primary, and secondary compression in bridge approach embankments built on soft soil, focusing on eliminating secondary compression using the preloading method, while the primary compression time is accelerated using Prefabricated Vertical Drains (PVD). Primary consolidation results in a 1.35-meter settlement, and secondary settlements vary over 20 years. From the analysis, it is found that the annual rate of secondary settlements decreases after year 10, so it is considered that the year 10 settlements are eliminated. To eliminate these settlements at year 10 of the operational period, the required embankment height increases by up to 13.60 meters of granular backfill, preloading of 4.49 t/m 2 is equivalent to 2.26 m, and the height of the embankment to be demolished is 1.85 m.

Authors

Institutions

Publication Details

Journal
Journal of Infrastructure & Facility Asset Management
Published
2025-01-28
DOI
https://doi.org/10.12962/jifam.v7i0.22482
Primary Topic
Geotechnical and construction materials studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Temporary Preloading for Bridge Approach Embankment to Eliminate Secondary Compression Case Study: Probolinggo – Banyuwangi Toll Road Construction Project Section 3 STA 40+550

Muhammad Rizal Permadi, Noor Endah Mochtar, Reza Kazhimi, Indrasurya B. Mochtar
Journal of Infrastructure & Facility Asset Management
Geotechnical and construction materials studies
article

Analysis of Temporary Preloading for Bridge Approach Embankment to Eliminate Secondary Compression Case Study: Probolinggo – Banyuwangi Toll Road Construction Project Section 3 STA 40+550

Muhammad Rizal Permadi, Noor Endah Mochtar, Reza Kazhimi, Indrasurya B. Mochtar
article en

Abstract

Probolinggo - Banyuwangi Toll Road is part of the National Strategic Project, has a length of 172 km which is divided into 7 sections. One of the challenges faced is soft soil, where information is obtained in section 3 precisely STA 40 + 550 there is soft soil, which has low bearing capacity and high compressibility. The depth of the soft soil itself reaches 10 meters, with the plan to build in the approach bridge area which has a 10 meter high embankment. Considering the high embankment, based on previous studies, it is estimated that the amount of primary and secondary compression generated is quite large. This study analyzes primary, and secondary compression in bridge approach embankments built on soft soil, focusing on eliminating secondary compression using the preloading method, while the primary compression time is accelerated using Prefabricated Vertical Drains (PVD). Primary consolidation results in a 1.35-meter settlement, and secondary settlements vary over 20 years. From the analysis, it is found that the annual rate of secondary settlements decreases after year 10, so it is considered that the year 10 settlements are eliminated. To eliminate these settlements at year 10 of the operational period, the required embankment height increases by up to 13.60 meters of granular backfill, preloading of 4.49 t/m 2 is equivalent to 2.26 m, and the height of the embankment to be demolished is 1.85 m.

Journal of Infrastructure & Facility Asset ManagementVol. 7(0)
Sepuluh Nopember Institute of Technology (ID), Universitas Panca Marga (ID)
Sustainable cities and communities
Openalex Percentile: Top 97%
Geotechnical and construction materials studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.