Life Cycle Risk Management for Improving Labor Productivity in Construction Projects in Türkiye

The construction industry, being labor-intensive, prioritizes productivity to boost project performance, yet struggles to achieve expected levels despite increased focus by scholars and practitioners. This lagging causes significant losses in time, cost, and quality performance of construction projects but also broader implications for resource efficiency and environmental impacts. As a remedy to the multifaceted issue, this study aims to identify and evaluate life cycle risks of productivity management in construction projects in Türkiye. A comprehensive literature review identified risk factors affecting labor productivity, followed by a discussion session to finalize the decision framework, including life cycle phases of productivity management and risk factors in each phase. Then, the fuzzy analytical hierarchy (AHP) process revealed the most critical risk factors in each phase, followed by semi-structured interviews to reveal measures for addressing the most significant risks. The findings show that productivity management in construction projects contains nine phases. In addition, the most important factors were chiefly related to collaboration, information sharing, lack of supervision, work interruptions, and changes. Findings from semi-structured interviews emphasize regular employee training and open communication to enhance project outcomes, optimize workflows, and promote sustainability. The study’s key contribution is introducing a life cycle approach to construction productivity management, a previously unexplored perspective. This provides an effective framework that can be implemented in construction projects to manage and improve labor productivity as a whole-life cycle approach.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-02-04
DOI
https://doi.org/10.3390/buildings15030484
Citations
5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
10.53
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Life Cycle Risk Management for Improving Labor Productivity in Construction Projects in Türkiye

Kerim Koç, Onur Şahin, Idil Calik
5 citations
Buildings
Construction Project Management and Performance
10.53
article

Life Cycle Risk Management for Improving Labor Productivity in Construction Projects in Türkiye

Kerim Koç, Onur Şahin, Idil Calik
article en
5 citations

Abstract

The construction industry, being labor-intensive, prioritizes productivity to boost project performance, yet struggles to achieve expected levels despite increased focus by scholars and practitioners. This lagging causes significant losses in time, cost, and quality performance of construction projects but also broader implications for resource efficiency and environmental impacts. As a remedy to the multifaceted issue, this study aims to identify and evaluate life cycle risks of productivity management in construction projects in Türkiye. A comprehensive literature review identified risk factors affecting labor productivity, followed by a discussion session to finalize the decision framework, including life cycle phases of productivity management and risk factors in each phase. Then, the fuzzy analytical hierarchy (AHP) process revealed the most critical risk factors in each phase, followed by semi-structured interviews to reveal measures for addressing the most significant risks. The findings show that productivity management in construction projects contains nine phases. In addition, the most important factors were chiefly related to collaboration, information sharing, lack of supervision, work interruptions, and changes. Findings from semi-structured interviews emphasize regular employee training and open communication to enhance project outcomes, optimize workflows, and promote sustainability. The study’s key contribution is introducing a life cycle approach to construction productivity management, a previously unexplored perspective. This provides an effective framework that can be implemented in construction projects to manage and improve labor productivity as a whole-life cycle approach.

BuildingsVol. 15(3)
Istanbul Bilgi University (TR), Yıldız Technical University (TR)
Openalex Percentile: Top 2%
Construction Project Management and Performance
10.53
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Life Cycle Risk Management for Improving Labor Productivity in Construction Projects in Türkiye — Kerim Koç, Onur Şahin, et al. · Buildings (2025) | TGRS Research Map | TGRS