Workload-Balancing Constraints in a Continuous-Time Integer Programming Formulation for the Resource-Constrained Project Scheduling Problem

In project management, the resource allocation problem consists of determining a schedule for the set of project activities that are related to each other by prescribed precedence relations and that require some time and some scarce resources to complete. In general, the goal is to minimize the project duration or time-to-market. In many cases, each resource represents a team of people with specific skills, such as engineering or marketing specialists. To promote team productivity and cohesion, it is often desirable to balance the workload within the team, i.e. among the resource units. We analyze two alternative approaches to formulate appropriate workload-balancing constraints in a mixed-binary linear optimization problem. In the first approach, the maximum deviation of each unit’s workload from the average workload is bounded, and in the second approach, the maximum workload difference between any pair of units is bounded. Our computational results for a standard test set from the literature show that balanced workloads can generally be achieved without increasing project duration; moreover, the second approach provides more flexibility, resulting in fewer instances for which no feasible solution exists.

Authors

Institutions

Publication Details

Published
2024-12-15
DOI
https://doi.org/10.1109/ieem62345.2024.10856996
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Workload-Balancing Constraints in a Continuous-Time Integer Programming Formulation for the Resource-Constrained Project Scheduling Problem

T. Bigler, Ν. Trautmann, N. Ackermann
Resource-Constrained Project Scheduling
article

Workload-Balancing Constraints in a Continuous-Time Integer Programming Formulation for the Resource-Constrained Project Scheduling Problem

T. Bigler, Ν. Trautmann, N. Ackermann
article en

Abstract

In project management, the resource allocation problem consists of determining a schedule for the set of project activities that are related to each other by prescribed precedence relations and that require some time and some scarce resources to complete. In general, the goal is to minimize the project duration or time-to-market. In many cases, each resource represents a team of people with specific skills, such as engineering or marketing specialists. To promote team productivity and cohesion, it is often desirable to balance the workload within the team, i.e. among the resource units. We analyze two alternative approaches to formulate appropriate workload-balancing constraints in a mixed-binary linear optimization problem. In the first approach, the maximum deviation of each unit’s workload from the average workload is bounded, and in the second approach, the maximum workload difference between any pair of units is bounded. Our computational results for a standard test set from the literature show that balanced workloads can generally be achieved without increasing project duration; moreover, the second approach provides more flexibility, resulting in fewer instances for which no feasible solution exists.

University of Bern (CH)
Openalex Percentile: Top 67%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.