Causes and Effects of Change Orders for Construction Projects in Palestine

The construction sector is vital to Palestinian economy, contributing significantly to its growth and development. Its complex nature encompasses human, non-human, and other elements and often necessitates change orders, which are inevitable, regardless of the project size, type, or characteristics. Change orders lead to massive delays and cost overruns impacting project timeline and profitability. The ccurrent study explores and ranks the causes and impacts of change orders in Palestinian construction projects from contractors' and consultants' perspectives. The findings revealed that internal factors related to the owner were the primary source of change orders. The major five causes were ranked based on the Relative Importance Index as follows: "use of duplicated documents from previous projects," "change in plan and scope by owner," "owner's financial difficulties," "poor site investigation before the design stage," and "errors and omissions in design." Similarly, the study presents the top five impacts of change orders as follows: "time overruns," "cost overruns," "rework and demolition," "delay in payment by the owner," and "disputes between contract parties." This study holds particular importance for the construction sector, offering valuable insights into managing the change orders to meet the projects objectives in terms of schedule, budget, and quality.

Authors

Institutions

Publication Details

Journal
Engineering Technology & Applied Science Research
Published
2025-02-01
DOI
https://doi.org/10.48084/etasr.8717
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Causes and Effects of Change Orders for Construction Projects in Palestine

Ibrahim Mahamid, Ahmad S. Abdelaal
Engineering Technology & Applied Science Research
Construction Project Management and Performance
article

Causes and Effects of Change Orders for Construction Projects in Palestine

Ibrahim Mahamid, Ahmad S. Abdelaal
article en

Abstract

The construction sector is vital to Palestinian economy, contributing significantly to its growth and development. Its complex nature encompasses human, non-human, and other elements and often necessitates change orders, which are inevitable, regardless of the project size, type, or characteristics. Change orders lead to massive delays and cost overruns impacting project timeline and profitability. The ccurrent study explores and ranks the causes and impacts of change orders in Palestinian construction projects from contractors' and consultants' perspectives. The findings revealed that internal factors related to the owner were the primary source of change orders. The major five causes were ranked based on the Relative Importance Index as follows: "use of duplicated documents from previous projects," "change in plan and scope by owner," "owner's financial difficulties," "poor site investigation before the design stage," and "errors and omissions in design." Similarly, the study presents the top five impacts of change orders as follows: "time overruns," "cost overruns," "rework and demolition," "delay in payment by the owner," and "disputes between contract parties." This study holds particular importance for the construction sector, offering valuable insights into managing the change orders to meet the projects objectives in terms of schedule, budget, and quality.

Engineering Technology & Applied Science ResearchVol. 15(1)
Palestinian Hydrology Group (PS), Arab American University (PS)
Openalex Percentile: Top 98%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.