Feasibility of Connecting Consumers in Isolated Communities to the Irkutsk Power System

The study summarizes key data on public power supply to isolated off-grid communities in the Irkutsk region. We compile a list of candidate settlements that qualify for grid extension and indicate the substations that in all likelihood will be used to feed them. This includes a multi-factor analysis of economic performance of power supply to such settlements. We report the findings of a technical and financial feasibility study of connecting remote communities to the power grid. The feasibility is assessed based on consolidated costs of the construction of power grid facilities. The study identifies the settlements where it is most economically viable to link them to the power grid. Additionally, we assess the feasibility of connecting two large off-grid industrial consumers in the mining industry to the power system. The successful completion of these projects is a prerequisite for connecting two communities in Tofalariya to the grid.

Authors

Institutions

Publication Details

Journal
Energy Systems Research
Published
2024-12-28
DOI
https://doi.org/10.25729/esr.2024.04.0008
Primary Topic
Arctic and Russian Policy Studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Feasibility of Connecting Consumers in Isolated Communities to the Irkutsk Power System

Roman Ivanov, Irina Ivanova, В.А. Шакиров
Energy Systems Research
Arctic and Russian Policy Studies
article

Feasibility of Connecting Consumers in Isolated Communities to the Irkutsk Power System

Roman Ivanov, Irina Ivanova, В.А. Шакиров
article en

Abstract

The study summarizes key data on public power supply to isolated off-grid communities in the Irkutsk region. We compile a list of candidate settlements that qualify for grid extension and indicate the substations that in all likelihood will be used to feed them. This includes a multi-factor analysis of economic performance of power supply to such settlements. We report the findings of a technical and financial feasibility study of connecting remote communities to the power grid. The feasibility is assessed based on consolidated costs of the construction of power grid facilities. The study identifies the settlements where it is most economically viable to link them to the power grid. Additionally, we assess the feasibility of connecting two large off-grid industrial consumers in the mining industry to the power system. The successful completion of these projects is a prerequisite for connecting two communities in Tofalariya to the grid.

Energy Systems ResearchVol. 7(4(28))
Melentiev Energy Systems Institute (RU)
Openalex Percentile: Top 57%
Arctic and Russian Policy Studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.