Feasibility Study of 500 Kv Line High-Voltage Reactor Out of Operation in a Hydropower Station

In the early stage of construction of a large hydropower station, in order to solve the problem that the 500 kV long-distance transmission line will lead to the increase of line charging power, a set of high-voltage shunt reactors were installed on the left bank of the hydropower station. In the actual operation process, the high resistance has many defects, which has caused great safety hazards to the safe and stable operation of the transmission line. At present, due to the change of power grid structure parameters and operation mode, it creates conditions for the out of high-voltage reactor. In order to prevent the impact on the transmission line after the exit of the high-voltage reactor, this paper calculates the power frequency overvoltage, secondary-arc current, recovery voltage and switching over-voltage after the exit of the high-voltage reactor, analyses the reactive power balance of the 500 kV power grid near the left bank power station, and verifies the phase modulation and voltage regulation level under the typical operation mode. The results show that the outlet of the hydropower station has the condition of safe operation without high-voltage reactor.

Authors

Institutions

Publication Details

Published
2024-12-13
DOI
https://doi.org/10.1109/icpes63746.2024.10856618
Primary Topic
Graphite, nuclear technology, radiation studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Feasibility Study of 500 Kv Line High-Voltage Reactor Out of Operation in a Hydropower Station

Lihua Li, Wei Li, Zuowei Shen, Lijun Mao et al.
Graphite, nuclear technology, radiation studies
article

Feasibility Study of 500 Kv Line High-Voltage Reactor Out of Operation in a Hydropower Station

Lihua Li, Wei Li, Zuowei Shen, Lijun Mao, Feng Chen, Peng Bao, Xiangxue Zeng
article en

Abstract

In the early stage of construction of a large hydropower station, in order to solve the problem that the 500 kV long-distance transmission line will lead to the increase of line charging power, a set of high-voltage shunt reactors were installed on the left bank of the hydropower station. In the actual operation process, the high resistance has many defects, which has caused great safety hazards to the safe and stable operation of the transmission line. At present, due to the change of power grid structure parameters and operation mode, it creates conditions for the out of high-voltage reactor. In order to prevent the impact on the transmission line after the exit of the high-voltage reactor, this paper calculates the power frequency overvoltage, secondary-arc current, recovery voltage and switching over-voltage after the exit of the high-voltage reactor, analyses the reactive power balance of the 500 kV power grid near the left bank power station, and verifies the phase modulation and voltage regulation level under the typical operation mode. The results show that the outlet of the hydropower station has the condition of safe operation without high-voltage reactor.

State Grid Corporation of China (China) (CN), Yangtze River Pharmaceutical Group (China) (CN)
Affordable and clean energy
Openalex Percentile: Top 83%
Graphite, nuclear technology, radiation studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.