Workload Analysis in Determining the Number of Workers Handling Delivery of Brake Master Cylinder Products at Company X

Company X is one of the largest automotive companies engaged in manufacturing in Indonesia. In company X, there is a section for shipping finished goods/products called the handling delivery section. In this research, a time study was carried out using the stopwatch time study method to obtain standard time, workload, and number of workers to complete the delivery handling process. From the analysis results, it was found that the average working time for PMH hand pallet activities was 327.92 seconds, and PMH forklift was 167.623 seconds. Then, based on working time/worker/day of 420 minutes or 25,200 seconds, with 438 product deliveries per day, the workload of five workers experienced an excess of PMH hand pallet 113.991% and PMH forklift 145.67%. With the addition of one worker for PMH hand pallet, and one worker for PMH forklift, the workload is not excessive, namely 94.99% for PMH hand pallet and 97.10% for PMH forklift.

Authors

Institutions

Publication Details

Journal
VANOS Journal of Mechanical Engineering Education
Published
2024-11-30
DOI
https://doi.org/10.30870/vanos.v9i2.28653
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Workload Analysis in Determining the Number of Workers Handling Delivery of Brake Master Cylinder Products at Company X

Sesmaro Max Yuda, Rocky Rocky, Dikky Antonius
VANOS Journal of Mechanical Engineering Education
Management and Optimization Techniques
article

Workload Analysis in Determining the Number of Workers Handling Delivery of Brake Master Cylinder Products at Company X

Sesmaro Max Yuda, Rocky Rocky, Dikky Antonius
article en

Abstract

Company X is one of the largest automotive companies engaged in manufacturing in Indonesia. In company X, there is a section for shipping finished goods/products called the handling delivery section. In this research, a time study was carried out using the stopwatch time study method to obtain standard time, workload, and number of workers to complete the delivery handling process. From the analysis results, it was found that the average working time for PMH hand pallet activities was 327.92 seconds, and PMH forklift was 167.623 seconds. Then, based on working time/worker/day of 420 minutes or 25,200 seconds, with 438 product deliveries per day, the workload of five workers experienced an excess of PMH hand pallet 113.991% and PMH forklift 145.67%. With the addition of one worker for PMH hand pallet, and one worker for PMH forklift, the workload is not excessive, namely 94.99% for PMH hand pallet and 97.10% for PMH forklift.

VANOS Journal of Mechanical Engineering EducationVol. 9(2)
Universitas Kristen Indonesia (ID)
Decent work and economic growth
Openalex Percentile: Top 54%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Workload Analysis in Determining the Number of Workers Handling Delivery of Brake Master Cylinder Products at Company X — Sesmaro Max Yuda, Rocky Rocky, et al. · VANOS Journal of Mechanical Engineering Education (2024) | TGRS Research Map | TGRS