Cost Estimation and Project Completion Time with Earned Value Analysis Approach on Waru-Buduran Frontage Road Project In Sidoarjo

The construction project of the Frontage Road Waru-Buduran in Sidoarjo has faced significant delays, highlighting the critical challenges in maintaining project efficiency. This study aims to analyze the cost and schedule estimates for the remaining work, as well as the total project completion using the Earned Value Analysis (EVA) method. The analysis results reveal a progress deviation of -9.911% by week 14 out of the total planned 21 weeks, indicating substantial schedule delays. Final completion estimates indicate a delay of 16.5 days and cost efficiency of IDR 1,246,797,954.06 (3.8%), demonstrating effective cost management despite schedule setbacks. EVA has proven effective in integrating cost and schedule performance indicators, such as Schedule Performance Index (SPI) and Cost Performance Index (CPI), to provide a comprehensive evaluation of project health. The findings emphasize the importance of early identification of deviations through EVA to implement corrective strategies, such as resource reallocation, schedule adjustments, and improved stakeholder coordination. The application of EVA enables project managers to predict potential risks, mitigate delays, and optimize resource utilization to achieve project objectives. This study provides valuable insights for project management practices, offering practical guidelines for addressing the complexities of construction projects. By utilizing EVA, project managers can ensure better decision-making, improve time and cost efficiency, and minimize conflicts arising from deviations in project execution. The findings serve as a reference for adopting EVA as a standard method in construction management to enhance overall project performance and ensure timely completion within budgetary constraints.

Authors

Institutions

Publication Details

Journal
Journal of Social Science (JoSS)
Published
2025-01-27
DOI
https://doi.org/10.57185/joss.v4i1.412
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Cost Estimation and Project Completion Time with Earned Value Analysis Approach on Waru-Buduran Frontage Road Project In Sidoarjo

Budi Witjaksana, Hanie Teki Tjendani, Suparno Suparno
Journal of Social Science (JoSS)
Occupational Health and Safety Management
article

Cost Estimation and Project Completion Time with Earned Value Analysis Approach on Waru-Buduran Frontage Road Project In Sidoarjo

Budi Witjaksana, Hanie Teki Tjendani, Suparno Suparno
article en

Abstract

The construction project of the Frontage Road Waru-Buduran in Sidoarjo has faced significant delays, highlighting the critical challenges in maintaining project efficiency. This study aims to analyze the cost and schedule estimates for the remaining work, as well as the total project completion using the Earned Value Analysis (EVA) method. The analysis results reveal a progress deviation of -9.911% by week 14 out of the total planned 21 weeks, indicating substantial schedule delays. Final completion estimates indicate a delay of 16.5 days and cost efficiency of IDR 1,246,797,954.06 (3.8%), demonstrating effective cost management despite schedule setbacks. EVA has proven effective in integrating cost and schedule performance indicators, such as Schedule Performance Index (SPI) and Cost Performance Index (CPI), to provide a comprehensive evaluation of project health. The findings emphasize the importance of early identification of deviations through EVA to implement corrective strategies, such as resource reallocation, schedule adjustments, and improved stakeholder coordination. The application of EVA enables project managers to predict potential risks, mitigate delays, and optimize resource utilization to achieve project objectives. This study provides valuable insights for project management practices, offering practical guidelines for addressing the complexities of construction projects. By utilizing EVA, project managers can ensure better decision-making, improve time and cost efficiency, and minimize conflicts arising from deviations in project execution. The findings serve as a reference for adopting EVA as a standard method in construction management to enhance overall project performance and ensure timely completion within budgetary constraints.

Journal of Social Science (JoSS)Vol. 4(1)
University of Surabaya (ID), Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 98%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Cost Estimation and Project Completion Time with Earned Value Analysis Approach on Waru-Buduran Frontage Road Project In Sidoarjo — Budi Witjaksana, Hanie Teki Tjendani, et al. · Journal of Social Science (JoSS) (2025) | TGRS Research Map | TGRS