Risk assessment of the causes of cost overrun of project XYZ

Cost overrun is a phenomenon that often occurs in the construction of a construction project. The purpose of this study is to analyze the main factors causing cost overrun in project XYZ based on the results of sensitivity analysis to the variables that form RAP. The results show that the cost element of subcontractors has a very large effect on the total RAP of the subcontractor, and the most dominant work affecting is steel work and panel sandwich work. The RAP weight of the work that affects the RAP is between 22.84% and 43.39%, followed by panel sandwich works and bridge steel work. It is recommended that PT X evaluate the performance of each related bureau, especially the estimating and engineering bureaus, in calculating RAP analysis and considering potential long-term risks.

Authors

Institutions

Publication Details

Journal
Indonesian Journal of Multidisciplinary Science
Published
2024-08-31
DOI
https://doi.org/10.55324/ijoms.v3i11.971
Primary Topic
Technology Assessment and Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk assessment of the causes of cost overrun of project XYZ

Siti Jahroh, Widodo Ramadyanto, S. Tekka Ramadhani
Indonesian Journal of Multidisciplinary Science
Technology Assessment and Management
article

Risk assessment of the causes of cost overrun of project XYZ

Siti Jahroh, Widodo Ramadyanto, S. Tekka Ramadhani
article en

Abstract

Cost overrun is a phenomenon that often occurs in the construction of a construction project. The purpose of this study is to analyze the main factors causing cost overrun in project XYZ based on the results of sensitivity analysis to the variables that form RAP. The results show that the cost element of subcontractors has a very large effect on the total RAP of the subcontractor, and the most dominant work affecting is steel work and panel sandwich work. The RAP weight of the work that affects the RAP is between 22.84% and 43.39%, followed by panel sandwich works and bridge steel work. It is recommended that PT X evaluate the performance of each related bureau, especially the estimating and engineering bureaus, in calculating RAP analysis and considering potential long-term risks.

Indonesian Journal of Multidisciplinary ScienceVol. 3(11)
IPB University (ID)
Openalex Percentile: Top 68%
Technology Assessment and Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.