PERBANDINGAN BIAYA DAN WAKTU KOMPONEN DINDING MENGGUNAKAN SISTEM KONVENSIONAL DAN SISTEM MODULAR GEDUNG FPSD UPI

<p><em> Over time, Indonesia's development is advancing. Conventional techniques are now thought to be less efficient in terms of time and expense. Because of this, we require a construction innovation which specifically the development of a modular system in order to decrease the cost and duration of construction activity. The factory-fabricated materials used in the modular technique are installed using a tower crane. For the conventional approach and the modular method which uses precast concrete for wall component work, the comparison research uses lightweight brick material. This research used cost and time variables as a comparison of wall work with conventional methods and modular methods. This study used the FPSD Building project of the Indonesian University of Education (UPI) for data collection which was then processed with Microsoft Excel software. This study aimed to analyze cost and time efficiency to determine the percentage of savings in the use of precast concrete as an alternative in the future. The results of this study for light brick wall work require a fee of IDR 5,648,755,562.71 and walls using precast concrete materials at a price of IDR 6,916,150,235.52. Meanwhile, in terms of time, the fastest wall work duration was wall work using precast concrete material, which was 138 days. Whereas the longest time for wall work was using lightweight brick material with a duration of 231 days.</em></p>

Authors

Institutions

Publication Details

Journal
Matriks Teknik Sipil
Published
2024-12-31
DOI
https://doi.org/10.20961/mateksi.v12i1.77641
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

PERBANDINGAN BIAYA DAN WAKTU KOMPONEN DINDING MENGGUNAKAN SISTEM KONVENSIONAL DAN SISTEM MODULAR GEDUNG FPSD UPI

Ary Setyawan, Adji Retno Kurniawati, Budi Utomo
Matriks Teknik Sipil
Management and Optimization Techniques
article

PERBANDINGAN BIAYA DAN WAKTU KOMPONEN DINDING MENGGUNAKAN SISTEM KONVENSIONAL DAN SISTEM MODULAR GEDUNG FPSD UPI

Ary Setyawan, Adji Retno Kurniawati, Budi Utomo
article en

Abstract

<p><em> Over time, Indonesia's development is advancing. Conventional techniques are now thought to be less efficient in terms of time and expense. Because of this, we require a construction innovation which specifically the development of a modular system in order to decrease the cost and duration of construction activity. The factory-fabricated materials used in the modular technique are installed using a tower crane. For the conventional approach and the modular method which uses precast concrete for wall component work, the comparison research uses lightweight brick material. This research used cost and time variables as a comparison of wall work with conventional methods and modular methods. This study used the FPSD Building project of the Indonesian University of Education (UPI) for data collection which was then processed with Microsoft Excel software. This study aimed to analyze cost and time efficiency to determine the percentage of savings in the use of precast concrete as an alternative in the future. The results of this study for light brick wall work require a fee of IDR 5,648,755,562.71 and walls using precast concrete materials at a price of IDR 6,916,150,235.52. Meanwhile, in terms of time, the fastest wall work duration was wall work using precast concrete material, which was 138 days. Whereas the longest time for wall work was using lightweight brick material with a duration of 231 days.</em></p>

Matriks Teknik SipilVol. 12(1)
Sebelas Maret University (ID)
Openalex Percentile: Top 55%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.