PERBANDINGAN BIAYA DAN WAKTU PEMBANGUNAN GEDUNG PASCASARJANA UPI DENGAN METODE MODULAR PADA DINDING

<p><em>The Indonesian University of Education faced project delays that had an impact on the budget and timing of the Postgraduate Building's development. The UPI Postgraduate Building is being constructed using traditional methods, which results in a lengthy amount of work. The aforesaid issue might have a solution in the modular approach. The modular approach can swiftly meet significant customer demands since it has a production technique for creating components that are mass-produced. The conventional method's implementation costs and timeline are being contrasted with the modular method's implementation costs and timeline. The cost and construction time of traditional walls and modular walls which use precast concrete materials and lightweight concrete panels are compared for wall components. To make the optimal decision, the analysis was done using the comparison technique and the cost-effectiveness analysis approach. From the results of the analysis, the use of precast concrete and lightweight concrete panels experienced cost inefficiencies of 17.92% and 11.75% but were able to save time 62.03% and 34.78% respectively. Based on the Cost Effectiveness Analysis, an alternative material that was a more cost-effective choice was precast concrete walls.</em></p>

Authors

Institutions

Publication Details

Journal
Matriks Teknik Sipil
Published
2024-12-31
DOI
https://doi.org/10.20961/mateksi.v12i2.77640
Primary Topic
Manufacturing Process and Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

PERBANDINGAN BIAYA DAN WAKTU PEMBANGUNAN GEDUNG PASCASARJANA UPI DENGAN METODE MODULAR PADA DINDING

Fajar Sri Handayani, Ary Setyawan, Gabriella Angelisa Claudia
Matriks Teknik Sipil
Manufacturing Process and Optimization
article

PERBANDINGAN BIAYA DAN WAKTU PEMBANGUNAN GEDUNG PASCASARJANA UPI DENGAN METODE MODULAR PADA DINDING

Fajar Sri Handayani, Ary Setyawan, Gabriella Angelisa Claudia
article en

Abstract

<p><em>The Indonesian University of Education faced project delays that had an impact on the budget and timing of the Postgraduate Building's development. The UPI Postgraduate Building is being constructed using traditional methods, which results in a lengthy amount of work. The aforesaid issue might have a solution in the modular approach. The modular approach can swiftly meet significant customer demands since it has a production technique for creating components that are mass-produced. The conventional method's implementation costs and timeline are being contrasted with the modular method's implementation costs and timeline. The cost and construction time of traditional walls and modular walls which use precast concrete materials and lightweight concrete panels are compared for wall components. To make the optimal decision, the analysis was done using the comparison technique and the cost-effectiveness analysis approach. From the results of the analysis, the use of precast concrete and lightweight concrete panels experienced cost inefficiencies of 17.92% and 11.75% but were able to save time 62.03% and 34.78% respectively. Based on the Cost Effectiveness Analysis, an alternative material that was a more cost-effective choice was precast concrete walls.</em></p>

Matriks Teknik SipilVol. 12(2)
Sebelas Maret University (ID)
Openalex Percentile: Top 61%
Manufacturing Process and Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

PERBANDINGAN BIAYA DAN WAKTU PEMBANGUNAN GEDUNG PASCASARJANA UPI DENGAN METODE MODULAR PADA DINDING — Fajar Sri Handayani, Ary Setyawan, et al. · Matriks Teknik Sipil (2024) | TGRS Research Map | TGRS