Analysis of Time and Budget Efficiency In The Bungur-Kedoyo Road Project Using Earned Value Method

The Bungur-Kedoyo road construction project in Tulungagung Regency represents a critical infrastructure initiative aimed at enhancing connectivity and transportation efficiency. However, challenges in managing time and cost effectively remain significant in ensuring project success. This study aims to evaluate the performance of the project using the Earned Value Method (EVM), a comprehensive framework that integrates cost and schedule analysis. EVM metrics, including Schedule Estimate To Completion (SETC), Schedule Estimate At Completion (SEAC), Budget Estimate To Completion (BETC), and Budget Estimate At Completion (BEAC), were employed to monitor and forecast project progress. The findings indicate that the project is largely on schedule, with an estimated additional week required to complete the remaining 96.908% of work, extending the contracted timeline of 180 days slightly. The remaining cost is projected at Rp. 273,570,437.28, and the total expenditure remains below the contract value at Rp. 8,847,685,552.51 out of Rp. 10,640,186,000. These results highlight the effectiveness of EVM in providing precise tracking and forecasting, ensuring the project stays within budget while achieving its objectives. The study concludes that EVM is a valuable tool for managing complex construction projects, offering actionable insights to improve time and cost efficiency for similar future endeavors.

Authors

Institutions

Publication Details

Journal
Asian Journal of Social and Humanities
Published
2025-01-22
DOI
https://doi.org/10.59888/ajosh.v3i4.477
Citations
1
Primary Topic
Value Engineering and Management
Type
article
Field-Weighted Citation Impact
2.23
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Time and Budget Efficiency In The Bungur-Kedoyo Road Project Using Earned Value Method

Sajiyo Sajiyo, Andi Patriadi, Moh. Bahrudin
1 citations
Asian Journal of Social and Humanities
Value Engineering and Management
2.23
article

Analysis of Time and Budget Efficiency In The Bungur-Kedoyo Road Project Using Earned Value Method

Sajiyo Sajiyo, Andi Patriadi, Moh. Bahrudin
article en
1 citations

Abstract

The Bungur-Kedoyo road construction project in Tulungagung Regency represents a critical infrastructure initiative aimed at enhancing connectivity and transportation efficiency. However, challenges in managing time and cost effectively remain significant in ensuring project success. This study aims to evaluate the performance of the project using the Earned Value Method (EVM), a comprehensive framework that integrates cost and schedule analysis. EVM metrics, including Schedule Estimate To Completion (SETC), Schedule Estimate At Completion (SEAC), Budget Estimate To Completion (BETC), and Budget Estimate At Completion (BEAC), were employed to monitor and forecast project progress. The findings indicate that the project is largely on schedule, with an estimated additional week required to complete the remaining 96.908% of work, extending the contracted timeline of 180 days slightly. The remaining cost is projected at Rp. 273,570,437.28, and the total expenditure remains below the contract value at Rp. 8,847,685,552.51 out of Rp. 10,640,186,000. These results highlight the effectiveness of EVM in providing precise tracking and forecasting, ensuring the project stays within budget while achieving its objectives. The study concludes that EVM is a valuable tool for managing complex construction projects, offering actionable insights to improve time and cost efficiency for similar future endeavors.

Asian Journal of Social and HumanitiesVol. 3(4)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 14%
Value Engineering and Management
2.23
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.