Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang

Construction projects have three targets that must be achieved, namely accuracy of cost, time and quality. These three targets are influenced by work productivity. However, in the implementation of construction projects there are often delays. So, contractors usually do various ways to catch up on project delays. One of the things that contractors do to speed up work is by adding working hours outside of regular working hours or overtime. When working during regular working hours, there will be different conditions during overtime, causing differences in productivity levels between the two. The amount of productivity produced is influenced by many factors. Factors, such as field conditions and supporting facilities, job skills, age, experience, and field management. This study was conducted using observation and questionnaire methods. The observation method is carried out by measuring the implementation of work during normal and overtime hours and recording activities. Questionnaires were distributed to workers to obtain factors that affect labor productivity. The results obtained were average productivity during normal hours of 2,018 m2/hour and overtime hours of 2,043 m2/hour. The average LUR value during normal working hours is 61.39% and overtime hours is 64.66%. In addition, factors that greatly influence are workers' wages, weather conditions, work area conditions, and lack of rest time.

Authors

Institutions

Publication Details

Journal
Jurnal Bangunan Konstruksi & Desain
Published
2024-09-30
DOI
https://doi.org/10.25077/jbkd.2.3.180-190.2024
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang

Benny Hidayat, Azdharizka Yunita
Jurnal Bangunan Konstruksi & Desain
Occupational Health and Safety Management
article

Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang

Benny Hidayat, Azdharizka Yunita
article en

Abstract

Construction projects have three targets that must be achieved, namely accuracy of cost, time and quality. These three targets are influenced by work productivity. However, in the implementation of construction projects there are often delays. So, contractors usually do various ways to catch up on project delays. One of the things that contractors do to speed up work is by adding working hours outside of regular working hours or overtime. When working during regular working hours, there will be different conditions during overtime, causing differences in productivity levels between the two. The amount of productivity produced is influenced by many factors. Factors, such as field conditions and supporting facilities, job skills, age, experience, and field management. This study was conducted using observation and questionnaire methods. The observation method is carried out by measuring the implementation of work during normal and overtime hours and recording activities. Questionnaires were distributed to workers to obtain factors that affect labor productivity. The results obtained were average productivity during normal hours of 2,018 m2/hour and overtime hours of 2,043 m2/hour. The average LUR value during normal working hours is 61.39% and overtime hours is 64.66%. In addition, factors that greatly influence are workers' wages, weather conditions, work area conditions, and lack of rest time.

Jurnal Bangunan Konstruksi & DesainVol. 2(3)
Andalas University (ID)
Openalex Percentile: Top 54%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang — Benny Hidayat, Azdharizka Yunita · Jurnal Bangunan Konstruksi & Desain (2024) | TGRS Research Map | TGRS