Borderless Fab Scenarios in Hierarchical Planning Settings: A Simulation Study

Lots are transferred in borderless fab (BF) scenarios from one wafer fab to another nearby fab to carry out process steps of the transferred lots. BF aims to compensate for scarce bottleneck capacity in some of the wafer fabs. One goal of the master planning function is to distribute the demand over the wafer fabs such that situations are avoided where large queues of lots arise in the wafer fabs. Due to inaccurate modeling of capacities and lead times in master planning, this goal is not always reached. Wafer fabs are often heretogenous. This leads to additional costs for BF scenarios which might make them less attractive. We are interested in exploring conditions with respect to master planning and wafer fab heterogeneity under which BF scenarios are still beneficial. Master planning, production planning, and the BF lot transfers are carried out in a rolling horizon setting using a cloud-based infrastructure.

Authors

Institutions

Publication Details

Published
2024-12-15
DOI
https://doi.org/10.1109/wsc63780.2024.10838849
Citations
1
Primary Topic
Cultural Industries and Urban Development
Type
article
Field-Weighted Citation Impact
1.96
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Borderless Fab Scenarios in Hierarchical Planning Settings: A Simulation Study

Lars Mönch, Raphael Herding
1 citations
Cultural Industries and Urban Development
1.96
article

Borderless Fab Scenarios in Hierarchical Planning Settings: A Simulation Study

Lars Mönch, Raphael Herding
article en
1 citations

Abstract

Lots are transferred in borderless fab (BF) scenarios from one wafer fab to another nearby fab to carry out process steps of the transferred lots. BF aims to compensate for scarce bottleneck capacity in some of the wafer fabs. One goal of the master planning function is to distribute the demand over the wafer fabs such that situations are avoided where large queues of lots arise in the wafer fabs. Due to inaccurate modeling of capacities and lead times in master planning, this goal is not always reached. Wafer fabs are often heretogenous. This leads to additional costs for BF scenarios which might make them less attractive. We are interested in exploring conditions with respect to master planning and wafer fab heterogeneity under which BF scenarios are still beneficial. Master planning, production planning, and the BF lot transfers are carried out in a rolling horizon setting using a cloud-based infrastructure.

Research Institute for Telecommunication Cooperation (DE)
Openalex Percentile: Top 10%
Cultural Industries and Urban Development
1.96
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.