Discrete Events Simulation of a Manufacturing Line for Floating Wind Turbines

This paper presents the simulation model developed for designing and optimizing a mass manufacturing plant of floating offshore wind units. The floating wind technology used for the analysis is CROWN FW, a competitive solution made of concrete and steel deck. To respond to the huge demand of the industry, mass production is necessary and the optimization of the construction sites and the logistic procedures highly valuable. The manufacturing line involves three workstations that produce floaters, two turbine assembly workstations and in land workstations for preassemblies. The simulation model has been implemented in Flexsim. The model has been parameterized to allow testing different procurement scenarios, task durations and planning of a 50 units program. It includes the effect of meteorological conditions like the windspeed or the tides height which can cause interruptions of some workstations. The results obtained in a first optimization run are discussed.

Authors

Publication Details

Published
2024-12-15
DOI
https://doi.org/10.1109/wsc63780.2024.10838720
Primary Topic
Advanced Manufacturing and Logistics Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Discrete Events Simulation of a Manufacturing Line for Floating Wind Turbines

Diego Crespo-Pereira, Santiago Bueno-Infantes, Daniel Molero-Medina, Sara Pereira-de la Infanta
Advanced Manufacturing and Logistics Optimization
article

Discrete Events Simulation of a Manufacturing Line for Floating Wind Turbines

Diego Crespo-Pereira, Santiago Bueno-Infantes, Daniel Molero-Medina, Sara Pereira-de la Infanta
article en

Abstract

This paper presents the simulation model developed for designing and optimizing a mass manufacturing plant of floating offshore wind units. The floating wind technology used for the analysis is CROWN FW, a competitive solution made of concrete and steel deck. To respond to the huge demand of the industry, mass production is necessary and the optimization of the construction sites and the logistic procedures highly valuable. The manufacturing line involves three workstations that produce floaters, two turbine assembly workstations and in land workstations for preassemblies. The simulation model has been implemented in Flexsim. The model has been parameterized to allow testing different procurement scenarios, task durations and planning of a 50 units program. It includes the effect of meteorological conditions like the windspeed or the tides height which can cause interruptions of some workstations. The results obtained in a first optimization run are discussed.

Affordable and clean energy
Openalex Percentile: Top 62%
Advanced Manufacturing and Logistics Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.