Financial Feasibility Analysis of Copper Cathode Factory at PT. X in Central Kalimantan

Indonesia has a lot of promising mineral wealth, one of which is copper, but its processing into cathodes is still minimal while domestic demand is not yet sufficient. In accordance with the strategic downstream investment plan for mineral commodities, especially copper, which has been included in the state downstream document, it requires a comprehensive financial feasibility document, especially for PT. X. The analysis in this research uses a reference capacity of 25,000 tons of cathode. This research aims to determine the technical factors in building a copper cathode factory, determine the amount of investment required in the form of CAPEX and OPEX, and determine its financial feasibility. The method used in financial feasibility analysis at PT. This X is Net Present Value (NPV), Internal Rate of Return (IRR), and Payback Period (PP). Based on the research results, it was found that the total CAPEX (Capital Expenditure) costs that had to be incurred were $ 330,589,628 and the total OPEX (Operational Expenditure) costs that had to be spent was $ 312,257,456 with an NPV value of $ 27,505,439, an IRR value of $ 27,505,439. 15.1%, and PP value for 6 years 10 months. Therefore, the project to build a copper cathode factory at PT. X is worth continuing.

Authors

Institutions

Publication Details

Journal
Sainteks Jurnal Sains dan Teknik
Published
2024-09-27
DOI
https://doi.org/10.37577/sainteks.v6i02.778
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Financial Feasibility Analysis of Copper Cathode Factory at PT. X in Central Kalimantan

Asep Hermawan, Dedy Setyo Oetomo, Syamsul Bahri
1 links
Sainteks Jurnal Sains dan Teknik
Management and Optimization Techniques
article

Financial Feasibility Analysis of Copper Cathode Factory at PT. X in Central Kalimantan

Asep Hermawan, Dedy Setyo Oetomo, Syamsul Bahri
article en

Abstract

Indonesia has a lot of promising mineral wealth, one of which is copper, but its processing into cathodes is still minimal while domestic demand is not yet sufficient. In accordance with the strategic downstream investment plan for mineral commodities, especially copper, which has been included in the state downstream document, it requires a comprehensive financial feasibility document, especially for PT. X. The analysis in this research uses a reference capacity of 25,000 tons of cathode. This research aims to determine the technical factors in building a copper cathode factory, determine the amount of investment required in the form of CAPEX and OPEX, and determine its financial feasibility. The method used in financial feasibility analysis at PT. This X is Net Present Value (NPV), Internal Rate of Return (IRR), and Payback Period (PP). Based on the research results, it was found that the total CAPEX (Capital Expenditure) costs that had to be incurred were $ 330,589,628 and the total OPEX (Operational Expenditure) costs that had to be spent was $ 312,257,456 with an NPV value of $ 27,505,439, an IRR value of $ 27,505,439. 15.1%, and PP value for 6 years 10 months. Therefore, the project to build a copper cathode factory at PT. X is worth continuing.

Sainteks Jurnal Sains dan TeknikVol. 6(2)
Universitas Purwakarta (ID)
Openalex Percentile: Top 55%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.