2-LEVEL CONSTRUCTION PLANNING MODEL WITH A LOCAL CASE STUDY

Two basic approaches underlie construction project management practices: Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). CPM widely used in the construction industry is criticized for its lacks of planning of repetitive or linear construction projects that contain the same or similar number of units such as mass housing. In this paper, a new 2-level location-based planning model (2-LCPM) has been presented to be used in the planning of construction projects consisting of repetitive activities and which is thought to eliminate the deficiencies of the existing models. It was designed at two levels: globally and locally. It provides a schedule with minimum delay to the planner at the global level while provides resource continuity at the local level. 2-LCPM was programmed in Go language and tested with a real case study by using Postman platform and SQL database. As a result, 2-LCPM is presented a new plan with increased resource continuity which are 5.32 %, 3.645% and 2.455% respectively, besides gives the same project complete time which is 15 months.

Authors

Publication Details

Journal
Revista Economica
Published
2024-12-31
DOI
https://doi.org/10.56043/reveco-2024-0015
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

2-LEVEL CONSTRUCTION PLANNING MODEL WITH A LOCAL CASE STUDY

Feyza Gürbüz, Gizem Erdinç
Revista Economica
BIM and Construction Integration
article

2-LEVEL CONSTRUCTION PLANNING MODEL WITH A LOCAL CASE STUDY

Feyza Gürbüz, Gizem Erdinç
article en

Abstract

Two basic approaches underlie construction project management practices: Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). CPM widely used in the construction industry is criticized for its lacks of planning of repetitive or linear construction projects that contain the same or similar number of units such as mass housing. In this paper, a new 2-level location-based planning model (2-LCPM) has been presented to be used in the planning of construction projects consisting of repetitive activities and which is thought to eliminate the deficiencies of the existing models. It was designed at two levels: globally and locally. It provides a schedule with minimum delay to the planner at the global level while provides resource continuity at the local level. 2-LCPM was programmed in Go language and tested with a real case study by using Postman platform and SQL database. As a result, 2-LCPM is presented a new plan with increased resource continuity which are 5.32 %, 3.645% and 2.455% respectively, besides gives the same project complete time which is 15 months.

Revista EconomicaVol. 76(2)
Openalex Percentile: Top 72%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.