Prioritization of Preventive Measures: A Multi-Criteria Approach to Risk Mitigation in Road Infrastructure Projects

Risk management in construction projects is a critical process aimed at identifying, evaluating, and mitigating potential risks that could impact project performance. Preventive measures play a central role in this process, serving as proactive strategies to minimize the likelihood and impact of risks on project outcomes. This study involved 37 experts from multidisciplinary fields related to road infrastructure, ensuring a diverse and comprehensive perspective on risk evaluation and prevention. The DELPHI method was employed to systematically define key risks and their corresponding preventive measures, providing a structured foundation for further analysis. The experts evaluated 302 preventive measures across 56 risks using 4 predefined criteria: implementation costs, time required for implementation, implementation complexity, and probability of success. A multi-criteria decision making (MCDM) approach was then applied to analyze these evaluations, enabling the prioritization of preventive measures and the allocation of resources toward the most effective strategies. Additionally, fuzzy logic was employed to analyze and validate the results, providing a complementary approach to the MCDM methodology. The results of this research provide a robust framework for risk management, offering practical guidance for decision makers in the construction industry. By integrating expert judgment, systematic evaluation, and advanced analytical methods, this study delivers actionable insights and establishes a reliable methodology for enhancing the effectiveness of risk mitigation in road infrastructure projects.

Authors

Institutions

Publication Details

Journal
Mathematics
Published
2025-01-16
DOI
https://doi.org/10.3390/math13020278
Citations
7
Primary Topic
Risk and Safety Analysis
Type
article
Field-Weighted Citation Impact
9.79
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Prioritization of Preventive Measures: A Multi-Criteria Approach to Risk Mitigation in Road Infrastructure Projects

Marija Ivanović, Momčilo Đobrodolac, Zoran Stojadinović, Aleksandar Senić
7 citations
Mathematics
Risk and Safety Analysis
9.79
article

Prioritization of Preventive Measures: A Multi-Criteria Approach to Risk Mitigation in Road Infrastructure Projects

Marija Ivanović, Momčilo Đobrodolac, Zoran Stojadinović, Aleksandar Senić
article en
7 citations

Abstract

Risk management in construction projects is a critical process aimed at identifying, evaluating, and mitigating potential risks that could impact project performance. Preventive measures play a central role in this process, serving as proactive strategies to minimize the likelihood and impact of risks on project outcomes. This study involved 37 experts from multidisciplinary fields related to road infrastructure, ensuring a diverse and comprehensive perspective on risk evaluation and prevention. The DELPHI method was employed to systematically define key risks and their corresponding preventive measures, providing a structured foundation for further analysis. The experts evaluated 302 preventive measures across 56 risks using 4 predefined criteria: implementation costs, time required for implementation, implementation complexity, and probability of success. A multi-criteria decision making (MCDM) approach was then applied to analyze these evaluations, enabling the prioritization of preventive measures and the allocation of resources toward the most effective strategies. Additionally, fuzzy logic was employed to analyze and validate the results, providing a complementary approach to the MCDM methodology. The results of this research provide a robust framework for risk management, offering practical guidance for decision makers in the construction industry. By integrating expert judgment, systematic evaluation, and advanced analytical methods, this study delivers actionable insights and establishes a reliable methodology for enhancing the effectiveness of risk mitigation in road infrastructure projects.

MathematicsVol. 13(2)
University of Belgrade (RS)
Openalex Percentile: Top 2%
Risk and Safety Analysis
9.79
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.