Settings Management with IED-Integrated Reporting Leads to Enhanced System Benefits

Device settings management, associated with the 500 MW expansion of an existing oil and gas facility’s 250 MW power system incorporating approximately 12,000 protective relays and other intelligent electronic devices, requires careful planning, defined commissioning processes, and meticulous change management administration. However, once systems are in place, loss-of-production events due to settings errors or relay manufacturer defects can be minimized in duration or eradicated completely when compared to traditional settings management methods.This paper presents an overview of the expanded power system, including intelligent electronic device-communications data flow, settings database structure, settings management, including the inventory of firmware and serial numbers, and an automated, facility-wide intelligent electronic device event report collection, as well as several examples in which automated, integrated reports resulted in a faster system restoration than was previously available at the facility. Sample events that resulted in an accelerated system restoration include a greenfield construction-area loss of source, a 60 MVA transformer energization, and the incorrect current transformer polarity leading to a line differential relay trip event.

Authors

Institutions

Publication Details

Published
2024-09-16
DOI
https://doi.org/10.1109/pcic47799.2024.10832162
Primary Topic
Non-Destructive Testing Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Settings Management with IED-Integrated Reporting Leads to Enhanced System Benefits

Michael T. Mendiola, M.T. Watkins, Kamran Heshami, Nilushan K. Mudugamuwa
Non-Destructive Testing Techniques
article

Settings Management with IED-Integrated Reporting Leads to Enhanced System Benefits

Michael T. Mendiola, M.T. Watkins, Kamran Heshami, Nilushan K. Mudugamuwa
article en

Abstract

Device settings management, associated with the 500 MW expansion of an existing oil and gas facility’s 250 MW power system incorporating approximately 12,000 protective relays and other intelligent electronic devices, requires careful planning, defined commissioning processes, and meticulous change management administration. However, once systems are in place, loss-of-production events due to settings errors or relay manufacturer defects can be minimized in duration or eradicated completely when compared to traditional settings management methods.This paper presents an overview of the expanded power system, including intelligent electronic device-communications data flow, settings database structure, settings management, including the inventory of firmware and serial numbers, and an automated, facility-wide intelligent electronic device event report collection, as well as several examples in which automated, integrated reports resulted in a faster system restoration than was previously available at the facility. Sample events that resulted in an accelerated system restoration include a greenfield construction-area loss of source, a 60 MVA transformer energization, and the incorrect current transformer polarity leading to a line differential relay trip event.

Albert Schweitzer Klinik (AT)
Openalex Percentile: Top 74%
Non-Destructive Testing Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Settings Management with IED-Integrated Reporting Leads to Enhanced System Benefits — Michael T. Mendiola, M.T. Watkins, et al. · (2024) | TGRS Research Map | TGRS